Md. Code Regs. 20.79.01.05 - Pre-Application Consultation Requirement for Generating Stations
A. A minimum of 90
days prior to filing an application for a Certificate of Public Convenience and
Necessity for the construction of a generating station, an applicant shall take
the following steps to engage and consult with the county or municipal
corporation in which any portion of the project is proposed to be located:
(1) Submit to the affected county or
municipal corporation the following:
(a) A
draft environmental review document in accordance with COMAR
20.79.03.02-.04;
(b) A properly
sized conceptual site plan for the project in accordance with COMAR
20.79.03.01;
(c) Where available for download on the
Commission's website, informational materials describing the Certificate of
Public Convenience and Necessity process and the process for intervention;
and
(d) A request for a meeting,
and the applicant shall make a good faith effort to meet with the staff of the
affected county or municipal corporation; and
(2) Request from the affected county or
municipal corporation a preliminary report containing the following:
(a) A statement or finding whether the
proposed project is consistent with the current comprehensive plan of the
county or municipal corporation;
(b) A statement or finding whether the
proposed project is consistent with the current zoning ordinance of the county
or municipal corporation; and
(c)
Suggestions for improving or modifying the application prior to submission of
the application with the Commission.
B. If the applicant makes any material
changes to the project as submitted under this regulation or as submitted to
the Commission under Regulation .06 of this chapter, the applicant shall
provide notice of the changes to the county or municipal corporation in which
any portion of the project is proposed to be located.
C. The applicant shall file with the
Commission any preliminary report or other updated information received from
the county or municipal corporation in which any portion of the project is
proposed to be located.
D. The
applicant shall, no later than 45 days prior to filing an application for a
Certificate of Public Convenience and Necessity for the construction of a
generating station, meet with the staff of the Department of Natural Resources
Power Plant Research Program to provide an overview of the proposed
project.