248 CMR, § 10.04 - Testing and Safety
(1)
Survey. Prior to the commencement of work, all
portions of existing systems that will be directly affected by proposed
plumbing work shall be surveyed by the licensed plumber to insure the existing
systems are adequate to support the proposed work.
(2)
Testing and Inspections of
the Plumbing System. All testing shall adhere to the
manufacturer's testing requirements of the materials being tested.
(a)
Testing and Inspection of
Rough Plumbing. Prior to requesting an inspection of rough
plumbing, the licensee shall choose one of the testing methods listed in
248
CMR 10.04 to ensure the safe and proper
functionality of the installed plumbing system. All testing shall be performed
in accordance with product manufacturer instructions.
Exception: The testing of plumbing systems in
manufactured and modular buildings shall be accomplished by performing a
non-destructive test and without removal of walls or other pre-fabricated
building components. The Inspector may require the permit holder or other
licensee employed by the permit holder to be on site, with
248 CMR
10.00.
1.
Methods of Testing the Drainage and Vent System.
a.
Water Test. A
water test shall be applied to the drainage system either in its entirety or in
sections. If applied to the entire system, all openings in the piping shall be
tightly closed, except the highest opening and the system filled with water to
point of overflow. If the system is tested in sections, each opening shall be
tightly plugged, except the highest opening of the section under test, and each
section shall be filled with water, but no section shall be tested with less
than a ten-foot head of water. When testing successive sections, at least the
upper ten feet of the next preceding section shall be tested, so that no joint
or pipe in the building (except the uppermost ten feet of the system) shall
have been submitted to a test that utilizes less than a ten-foot head of water.
The water shall be kept in the system or in the portion under test for at least
15 minutes before the inspection starts: the system shall then be tight at all
points.
b.
Air
Test. An air test shall be performed by attaching an air
compressor testing apparatus to any suitable opening, and, after closing all
other inlets and outlets to the system, forcing air into the system, until
there is a uniform gauge pressure of five PSIG or enough pressure to balance a
column of mercury ten inches in height. This pressure shall be held without
introduction of additional air for a period of at least fifteen minutes. The
gauge used for this test shall be calibrated in increments no greater than
1/10 of a pound.
d.
Peppermint
Test. A peppermint test shall only be used and performed on the
concealed piping within existing buildings or structures. The test shall be
applied by creating a liquid mixture with the appropriate amount of oil of
peppermint and hot water. The mixture shall be poured down a main stack. The
stack opening shall then be sealed. The individual who has handled the oil of
peppermint or the peppermint mixture shall not enter the building until the
test has been completed. The presence of the aroma of the oil of peppermint may
potentially be present on the individual who created the mixture and will
compromise the building environment under test and observation.
e.
Smoke Test. A
smoke test shall be performed by obtaining smoke injector equipment designed
for the purpose of producing and introducing a heavy volume of smoke. Smoke
injector testing equipment utilizes several methods for producing adequate
smoke conditions for testing; manufacturers' recommendations shall be observed.
The discharge hose from the smoke injector equipment shall be extended to and
through a smoke test cap or plug and all voids encompassing the hose shall be
sealed with putty or another similar compound. When the entire system or
portion thereof is charged with smoke, air pressure equal to U2 water column
shall be applied. Defects, failures, and leaks in the piping system will be
revealed by plumes of smoke that will discharge through
them.
2.
Methods of Testing the Water Distribution and Supply
System. Upon completion of a section or of the entire water supply
system when roughed, it shall be tested and proved tight under a pressure not
less than 125 pounds per square inch. Water used for tests shall be obtained
from a potable supply source. Air or other inert gases may be used for
testing.
(b)
Testing and Inspection of Finish Plumbing. When work
is ready for inspection, notice shall be given to the Inspector as required by
248
CMR 3.05(3)(d)1. within five
days after the plumbing work is complete.
(c) Within two working days after receipt of
such notice, the Inspector shall proceed with the inspection and examine the
work with the water turned on to the fixtures. The Inspector may require the
permit holder or other licensee employed by the permit holder to be on site,
with 248 CMR
10.00.
(d)
If the installation is found in compliance with 248 CMR an Inspection approval
tag shall be issued by the Inspector.
(e)
Grease
Interceptors. Interceptors must be isolated from the drainage
system prior to rough or final inspection. The interceptor must not be
subjected to air, water, or any other type of pressure
test.
(3)
Defects.
(a) Should
inspection of the permitted plumbing work disclose any defects or violations of
248 CMR the permit holder shall be required to remedy the violations and
defects, without delay, and notify the inspector for a repeat inspection of the
installation.
(b) If the licensee
holding a permit for work in a building turns the water on and fails to
properly notify the Inspector as required, or neglects to remedy any defects or
violations disclosed by the Inspector shall not be granted any further permits
until the defects have been rectified and/or the final inspection has been
performed.
(4)
Repairs and Alterations.
(a) Deviations from the provisions of 248 CMR
may be permitted in existing buildings or where plumbing installations are to
be altered, repaired, or renovated. The deviations shall be determined and
agreed upon by the permit holder and the inspector prior to the installation.
The deviations may be allowed provided they are found to be necessary and
conform to the scope and intent of
248 CMR
10.00.
(b)
Whenever compliance with the provisions of
248 CMR
10.00 fails to eliminate or alleviate a nuisance that
may involve health or safety hazards, the Inspector shall notify the owner or
the owner's agent in writing regarding the violations and the proper procedures
necessary to become compliant.
248
CMR 10.04 shall not be deemed as an allowance
to permit waivers from the material provisions of
248
CMR 10.06 or the fixture requirements of
248
CMR
10.10(15).
(5)
Defective
Plumbing.
(a) Whenever there is
reason to believe that the plumbing system of any building has become
defective, it shall be subjected to test and/or inspection. The Inspector shall
notify the owner or the owner's agent in writing regarding the defective
plumbing and the proper procedures necessary to become compliant.
(b) Whenever the work subject to a permit
complies with the provisions of
248 CMR
3.00 through
10.00, but the Inspector
notes other existing plumbing or gas fitting that may cause a health or safety
hazard, the Inspector shall notify the owner or the owner's agent in writing
regarding the violations and the proper procedures necessary to become
compliant.
(6)
Demolition and Removal.
(a) When a fixture that is connected to the
plumbing system is to be permanently removed, a permit for the work shall be
secured. All plumbing connections to that fixture shall be made water and gas
tight.
(b) Insofar as they are
pertinent, the provisions of
248
CMR 10.04(6)(a) shall also
apply when a building, structure, dwelling or tenant space is to be
demolished.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.