248 CMR, § 8.05 - Modifications to Chapter 6, Installation of LP-gas Systems

(1) This code does not adopt sub-section 6.1.1*(2) and (3).
(2) This code does not adopt sub-sections 6.2 to 6.7.10.
(3) This code adopts sub-section 6.8 to the extent it applies to second stage regulators, however it does not adopt those portions applying to first-stage or two-stage regulators.
(4) This code does not adopt sub-sections 6.10 to 6.13.
(5) Delete sub-section 6.15 and replace it with the following:

6.15: Installation in Areas of Heavy Snowfall. Piping, regulators, meters, and other equipment installed in the piping system, when exposed to the elements, must be protected from damage from accumulated snow by either following manufacturer's installation instructions when specific to such issues or, when no such instruction is provided, by otherwise reinforcing and/or sheltering any exposed equipment. However, should the performance of gas-fitting work impact the structural integrity of building or roofing components, necessary corrective work falls outside the scope of this code. See 780 CMR: The Massachusetts State Building Code or 271 CMR: The Massachusetts Sheet Metal Code, if applicable, for licensing and other requirements for said work.

(6) This code does not adopt sub-sections 6.16, 6.18, and 6.21 to 6.26.

Notes

248 CMR, § 8.05
Amended by Mass Register Issue 1275, eff. 12/5/2014.

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.