310 CMR, § 19.107 - Construction Certification
(1) The
construction of a permitted landfill shall be accomplished in compliance with a
quality assurance/quality control (QA/QC) plan approved by the
Department.
(2) The owner or
operator shall hire an independent professional Massachusetts registered
engineer, knowledgeable and experienced in matters of landfill construction who
shall oversee all construction activities. The engineer shall:
(a) determine and certify that all materials
and construction of the landfill adheres to approved design plans and
specifications, including:
1. determining the
initial and final grades of the landfill;
2. overseeing the installation and
construction of all components of the liner or final cover;
3. overseeing the installation and completion
of run-on and run-off controls, pumps, monitoring devices and other
appurtenances.
(b)
oversee material and equipment QA/QC testing and verify all data generated
through the testing program;
(c)
ensure that as-built plans, where required, accurately reflect the constructed
facility; and
(d) document all
construction and QA/QC activities.
(3) Liners and final covers shall be
constructed under the direction of a person with extensive experience in the
installation of liners and final caps. Each phase of construction of a liner or
cap shall be carried out and inspected under the direction of the independent
professional engineer who shall certify that each phase of construction was
completed in accordance with approved plans and specifications.
(4) The owner or operator shall submit a copy
of the engineer's certification, as required at
310 CMR
19.011 on all construction and QA/QC
activities to the Department.