310 CMR, § 80.16 - Installation Requirements
(1) No UST system
shall be installed except by a person who has been certified to install that
type of UST system in writing by the UST system manufacturer. The installation
shall include, but shall not be limited to, compliance with the manufacturer's
specifications and all items on the manufacturer's checklist(s).
(a) The installer shall certify that the UST
system was installed in accordance with the manufacturer's specifications and
that the installer complied with all items on the manufacturer's installation
checklist(s).
(b) The Owner or
Operator shall maintain a copy of the certifications in 310 CMR 80.16(1) and
80.16(1)(a), manufacturer's specifications and completed checklist(s) in
accordance with
310 CMR
80.36.
(c) The Owner shall submit the installer
certification(s) from the manufacturer(s) and the installer's certification in
310 CMR 80.16(1)(a), in accordance with
310 CMR
80.23(1)(b).
(d) A new double-walled tank may be installed
inside an existing tank, if the new double-walled tank meets the requirements
of
310 CMR
80.17 and does not rely on the existing tank
to provide structural integrity or as a tank wall and:
1. Prior to installing the new double-walled
tank, the Owner or Operator shall have all the solid and liquid material
removed from the existing UST system, in accordance with
310 CMR
80.47, have the existing UST system rendered
inert and shall secure all openings. The Owner or Operator shall manage all
solid and liquid material removed from the UST system in accordance with all
applicable federal, state and local laws and regulations.
2. Conduct an assessment in accordance with
310 CMR
80.43(4) before the new
double-walled tank is installed. If the assessment finds contamination
requiring notification pursuant to 310 CMR 40.0000, Massachusetts
Contingency Plan, the installation of the new tank shall not commence
until the Owner or Operator has complied with the notification requirements
contained in
310
CMR 40.0300: Notification of Releases
and Threats of Release of Oil and Hazardous Materials; Identification and
Listing of Oil and Hazardous Materials, as applicable, and any
required response actions under 310 CMR 40.0000.
3. Notify the Department that a new
double-walled tank is being installed inside an existing tank, in a format
specified by the Department, within 30 days of the new tank being installed. A
copy of the assessment in
310 CMR
80.43(4) shall be submitted
with said form.
(2) The installation of all UST systems,
including anchoring of the tank, shall be carried out in accordance with the
manufacturer's specifications, listed engineering practices, and the provisions
of
310 CMR
80.14 through
80.22.
In lieu of the requirements at 310 CMR 80.16(9) through (16),
Owners and Operators may use military construction criteria, such as Unified
Facilities Criteria (UFC) 3-460-01, Petroleum Fuel Facilities, when designing,
constructing, and installing UST systems with field-constructed tanks over
50,000 gallons capacity.
(3) Any
damage to the exterior of a tank or its coating shall be repaired before the
tank is covered.
(4)
The Tank and Piping Shall Pass the following Tests Prior to
Burial.
(a) The tank and the
interstitial space shall be tested by air pressure not less than three pounds
and not more than five pounds per square inch. If the interstitial space
contains liquid, testing shall comply with the manufacturer's
specifications.
(b) The piping
shall be hydrostatically tested (or by air pressure) to 150% of the maximum
anticipated pressure of the piping system, but not less than 50 pounds per
square inch gauge of the highest point of the piping system.
(c) The Owner shall provide the test results
to the professional engineer conducting the inspection in accordance with 310
CMR 80.16(6).
(5) After
installation, backfilling and surfacing to grade, the tank and piping shall
pass a tightness test in accordance with
310 CMR
80.32.
(6) All UST systems shall be inspected by the
person who prepares the drawings or as-built plans in accordance with 310 CMR
80.16(7), or their designated representative, prior to being backfilled, to
ensure the UST system is installed in accordance with
310 CMR
80.14 through
80.22.
If the person who prepares the drawing or as-built plans, or their designated
representative, determines the UST system is not installed in accordance with
310 CMR
80.14 through
80.22,
the UST system shall not be backfilled until the Owner or Operator of the UST
system complies with all requirements at
310 CMR
80.14 through
80.22.
(7) The Owner or Operator shall maintain a
scaled drawing or a set of as-built plans prepared by the installer who
installed the UST system or a registered professional engineer until the UST
system is removed or permanently closed in accordance with
310 CMR
80.43(2) or (3) and shall
submit a copy of the as-built plans to the Department in accordance with
310 CMR
80.23(1). The scaled drawing
or as-built plans shall include, but not be limited to:
(a) A locus plan or location map showing the
location of the UST facility and the global positioning system (GPS)
coordinates of the UST system(s). The plan or map shall include, but not be
limited to, the location of any public well, private well, if readily
ascertainable, and any body of surface water within 500 feet of the UST
facility. All drinking water wells shall be clearly marked on the plan or
map.
(b) A site plan of the UST
facility including, but not limited to, the location of each UST system and all
buildings.
(c) UST system details
including, but not limited to, a list of UST components (including manufacturer
and model number), schematics of the tanks, piping, and turbine, intermediate
and dispenser sumps, elevations of each tank and related piping below the final
surface grade and a materials list.
(d) A signed statement by the licensed
professional engineer who signed and sealed the as-built plans that the UST
system was installed in accordance with
310 CMR 80.00, the
manufacturer's specifications and the manufacturer's
checklist.
(8) The Owner
shall submit a registration to the Department within 30 days of the initial
introduction of regulated substance into an UST system on a form specified by
the Department, in accordance with
310 CMR
80.23(1), except Owners of
UST systems used solely for emergency spill or overflow containment shall
submit a registration to the Department within 30 days of
installation.
(9) If the
manufacturer's specifications do not specify the type of backfill material, the
Owner or Operator shall comply with one of the following:
(a) API Recommended Practice 1615,
6th Edition, April 2011, Installation of
Underground Petroleum Storage Systems; or
(b) PEI Recommended Practice 100-17, 2017,
Recommended Practices for Installation of Underground Liquid Storage
Systems.
(10) At
any fueling facilities where tanks are at an elevation which produces a gravity
head on the dispensing unit, the tank outlet shall be equipped with a device,
such as a solenoid valve, positioned adjacent to, and downstream from, the
outlet of the tank that is installed and adjusted so that liquid cannot flow by
gravity from the tank in case of piping or hose failure when the dispenser is
not in use.
(11) Underground piping
and underground vent lines shall be installed in a trench. If the
manufacturer's specifications specify a different standard for installing
piping and vent lines, the Owner and Operator may comply with the
manufacturer's specification in lieu of 310 CMR 80.16(11). The
Owner or Operator shall keep records of the standard in accordance with
310 CMR
80.36.
(12) A minimum six-inch-deep bed of
well-compacted noncorrosive material such as clean washed sand or gravel shall
be placed in a trench before the piping is installed, unless otherwise directed
by the manufacturer's specifications. All trenches shall be wide and deep
enough to permit at least six inches of noncorrosive backfill material
surrounding all lines, unless otherwise directed by the manufacturer's
specifications. The owner or Operator shall keep records of the Manufacturer's
specification in accordance with
310 CMR
80.36.
(13) All piping shall lead from the tops of
tanks, and the tops of all tanks shall be below the level of the lowest
horizontal pipe used in the connection therein, except where the design
specifically prevents a possible siphoning condition.
(14) All pipes used for the conveyance of
flammable liquid shall decline to tanks without traps or pockets, and shall be
protected against damage. Intermediate sumps installed to allow piping to
decline to tanks shall not be considered a trap or pocket provided the
intermediate sump is monitored for leakage and is accessible for repairs and
inspections. Piping drops from submerged pumps to allow piping decline to the
tank shall not be considered a trap. Siphon lines shall be exempt from 310 CMR
80.16(14).
(15) A double elbow
swing joint or flexible connector listed for underground applications shall be
installed at all locations where piping changes direction from horizontal to
vertical or from vertical to horizontal. If the manufacturer's specifications
specify a different standard, the Owner and Operator may comply with the
manufacturer's specification in lieu of 310 CMR 80.16(15). The
Owner or Operator shall keep records of the standard in accordance with
310 CMR
80.36.
(16) Pressurized systems shall be designed or
equipped so that no part of the system will be subjected to pressures above its
allowable working pressure in accordance with the manufacturer's
specifications.
(17) A permanent
dewatering well for the purpose of dewatering the tank grave in order to
conduct repairs of the UST system may be installed if the well is seated in the
tank grave and the well seals are designed and constructed to prevent migration
of fluids from the ground surface into the borehole.
(a) The following seals are all required and
shall be designed and constructed as follows:
1.
Annular Seals.
a. Annular seals shall be placed in the
annular space between the well casing and the borehole wall and above the
divider seal.
b. Annular seals
shall consist of a low permeability material that will serve to inhibit the
vertical movement of fluids within the annular space.
c. An annular seal shall be composed of one
or a combination of the following sealants: neat cement, bentonite/cement
slurries, or equivalent sealing agents.
2.
Divider Seals.
a. Divider seals shall consist of a layer of
bentonite slurry or pellets designed to prevent the annular seal materials from
plugging up the screened area of the well.
b. Divider seals shall be placed above the
material surrounding the well screen and below the annular seal.
3.
Surface (Apron)
Seal.
a. A surface seal around
the top of the well is required even if the annular seal is carried to the
surface.
b. A surface seal shall be
concrete.
c. A surface seal shall
be shaped so that surface water flows away from the well casing.
d. Based on site conditions, the surface seal
shall extend, at a minimum, to the bottom of the tank pad, and in no event less
than one foot below grade to prevent frost-heaving of the apron.
(b) Dewatering wells and
seals shall be maintained so as to prevent storm water and/or regulated
substances from entering the subsurface as long as the dewatering well is in
place.
(18) The Owner or
Operator shall keep a copy of the installer's certifications, manufacturer's
specifications and completed checklist(s), records of all testing results and
inspections conducted during the installation and the accurate drawing or
as-built plans in accordance with
310 CMR
80.36.