454 CMR, § 28.09 - Notification of Asbestos Project
An
(1) Notification must be on forms jointly
prescribed by the Director and the MassDEP.
(2) Notification must be
electronically-filed, postmarked or hand-delivered at least ten working days
before the project start date or, in the case of an Emergency Project , within
one working day after the project start date.
(a) Notification must be cancelled, amended,
edited and/or resubmitted if work dates change. Intermittent work notifications
may be updated by email or phone to the Department as allowed under
310 CMR
7.15(6)(g)4.
(b) Asbestos Contractors who notify for a
project and are found to be working during dates not covered by the
notification are in violation.
(c)
Asbestos Contractors who notify for a project and are found to NOT be working
during dates covered by the notification are in violation.
(3) Fulfillment of the asbestos project
notification requirements of the MassDEP through submission of a completed
Notification Form ANF-001 (BWP AQ-04) with the appropriate fee where required,
satisfies the notification requirements of
454
CMR 28.09.
(4) Fulfillment of the notification
requirements of
454
CMR 28.09 shall not relieve the Asbestos
Contractor , operator of the project or facility owner of the responsibility for
making written notification as may be required by any other municipality,
agency of the Commonwealth, or any agency of the federal government.