974 CMR, § 1.08 - Time Limits for Review
Each
TABLE 3: TIME LIMITS FOR REVIEW
Time Limit in Days |
|
Level One Review |
|
Lotting Plan |
14 |
|
21 |
Engineering Adjustment |
14 |
Building or Occupancy Permit |
30 |
Other reviews authorized in the |
21 |
Level Two Review |
(inclusive of the date of the DEC's |
Site Plan Review |
75 |
|
75 |
Wetlands |
63 |
Variances |
90 |
Reconsiderations (measured from the date of the request) |
45 |
Historic District Certificates of Appropriateness |
45 |