20 CSR 4240-3.140 - Filing Requirements for Applications for Authority for a Change of Electrical Suppliers
(1) In addition to the requirements of
4 CSR
240-2.060(1), applications for the
approval of a change in electrical suppliers shall include:
(A) A description of the type of structure
where the change of supplier is sought, and the street address, if any, of the
structure;
(B) The name and address
of the electrical supplier currently providing service to the
structure;
(C) The name and address
of the electrical supplier to which the applicant wishes to change;
(D) The applicant's reasons for seeking a
change of supplier;
(E) If the
applicant's reasons involve service problems, a description of the problems and
dates of occurrence, if known;
(F)
If the applicant's reasons involve service problems, a description of the
contacts which applicant has had with the current supplier regarding the
problems, if any, and what efforts the current supplier has made to solve the
problems, if any;
(G) The reasons a
change of electrical suppliers is in the public interest;
(H) If the current electrical supplier and
the requested electrical supplier agree to the requested change, a verified
statement for each supplier with the application, indicating agreement;
and
(I) If the applicant is an
electrical supplier, a list of the names and addresses of all customers whose
electrical supplier is proposed to be changed.
(2) If any of the items required under this
rule are unavailable at the time the application is filed, they shall be
furnished prior to the granting of the authority sought.