Mont. Admin. r. 10.75.106 - ADMINISTRATIVE PROCEDURES AND REQUIREMENTS
(1) Recipients must use an accounting system
that conforms to Generally Accepted Accounting Principles (GAAP), in accordance
with 18-4-311, MCA.
(2) Payment for approved expenses under the
contract will be paid in a single lump sum after receipt of the following
required forms:
(a) W-9 Form;
(b) electronic deposit form;
(c) a completed cash request through
Egrants;
(d) subrecipient agreement
form, if funds are to be deposited directly with a designee; and
(e) expenditure and progress reports and any
requested follow-up information submitted to and accepted as sufficient by the
Office of Public Instruction.
(3) Any additional project payments for
additional deliverables will be identified in amended contracts with the
grantees.
(4) If unexpected funds
have the potential of reverting to the general fund during the fourth quarter
of the state's fiscal year, which begins April 1, the Office of Public
Instruction may contract directly with an established subrecipient in an amount
proportionate to the unexpended funds.
(5) Contracts that are funded are subject to
disclosure, in response to requests received under provisions of the Montana
Constitution (Article II, Section 9). Information that could reasonably be
considered proprietary, privileged, or confidential in nature should be
identified as such in the contract.
(6) In performing the work on the project,
the grantee must comply with all applicable tribal, state, federal, and local
laws, ordinances, and regulations, including any necessary cultural review, and
obtain all permits, licenses, etc., required to perform the project. If the
program funds are used in conjunction with funds from federal sources,
compliance with additional federal regulations and laws may apply.
(7) The grantee must return to the Office of
Public Instruction all funds that are determined by the Office of Public
Instruction to have been spent in violation of the grant contract. In addition,
any reports mentioned in this subchapter that have not been received by the
Office of Public Instruction will result in the grantee being denied approval
to receive funds for the following year. If the work or the project is
determined to not have been performed or completed as contracted, the Office of
Public Instruction reserves the right to declare a default on the contract and
demand all funds of the contract be returned to the Office of Public
Instruction.
(8) Any requested
changes to the original scope of work or budget adjustments must be submitted
in writing to the Office of Public Instruction. The Office of Public
Instruction will determine if the request aligns with the program guidelines
which includes all requirements noted in this rule.