Mont. Admin. r. 38.5.8601 - DEFINITIONS
In this subchapter the following definitions shall apply unless the context otherwise clearly demands:
(1) "Interruption" means a loss of service to
one or more customers.
(2)
"Interruption duration" means the period of time, in minutes, between the time
an electric utility first becomes aware of a service interruption and the time
of restoration of service to the customer(s).
"Major event" means a catastrophic event that:
(a) for regulated electric utilities that
have adopted the Institute of Electrical and Electronic Engineers Guide for
Electric Power Distribution Reliability Indices, meets the definition of "major
event day," standard 1366-2003; or
(b) for regulated electric utilities that
have not adopted the Institute of Electrical and Electronic Engineers Guide for
Electric Power Distribution Reliability Indices:
(i) exceeds the design limits of the electric
power system;
(ii) causes extensive
damage to the electric power system; and
(iii) results in a simultaneous sustained
electric service interruption to more than 10% of the customers in an operating
area.
(4)
"Operating area" means a geographical subdivision of an electric utility's
Montana service territory that is a distinct area for administration,
operation, or data collection. These areas may also be referred to as regions,
divisions, or districts.