Mont. Admin. r. 38.5.8610 - GENERAL OBLIGATIONS OF ENERGY UTILITIES
(1) Each energy utility shall make reasonable
efforts to avoid and prevent interruptions of service. However, when
interruptions occur, service shall be reestablished within the shortest time
practicable, consistent with safety and good utility practices.
(2) Each energy utility's transmission and
distribution facilities shall be designed, constructed, maintained, reinforced,
and supplemented as required to reliably perform the natural gas and power
delivery burden placed upon them in the storm and traffic hazard environment in
which they are located.
(3) Each
energy utility shall carry on an effective preventive maintenance program and
shall be capable of emergency repair work on a scale which its storm and
traffic damage record indicates as appropriate to its scope of operations and
to the physical condition of its transmission and distribution
facilities.
(4) In appraising the
reliability of the electric utility's transmission and distribution system, the
commission will consider the condition of the physical property and the size,
training, supervision, availability, equipment, and mobility of the maintenance
forces, all as demonstrated in actual cases of storm and traffic damage to the
facilities.
(5) Each energy utility
shall keep records of interruptions of service on its primary distribution
system and shall make an analysis of the records for the purpose of determining
steps to be taken to prevent recurrence of such interruptions.
(6) Each energy utility shall make reasonable
efforts to reduce the risk of future interruptions by taking into account the
age, condition, design, and performance of transmission and distribution
facilities and providing adequate investment in the maintenance, repair,
replacement, and upgrade of facilities and equipment.