129 Neb. Admin. Code, ch. 1, § 033 - "Commence"

"Commence" as applied to construction, reconstruction, or modification of a stationary source means that the owner or operator has all necessary preconstruction approvals and either has:

033.01 Begun, or caused to begin, a continuous program of physical on-site construction of the source to be completed within a reasonable time; or
033.02 Entered into binding agreements or contractual obligations, which cannot be cancelled or modified without substantial loss to the owner or operator, to undertake a program of construction of the source to be completed within a reasonable time.

Notes

129 Neb. Admin. Code, ch. 1, § 033
Amended effective 7/15/2018

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.