Nev. Admin. Code § 338.630 - Proposals: Opening; qualifications

1. A construction manager at risk shall open proposals submitted by subcontractors who were qualified to submit proposals in accordance with the provisions of subsection 7 of NRS 338.16995.
2. Before the construction manager at risk opens a proposal submitted by a subcontractor, the construction manager at risk must confirm that the proposal was:
(a) Submitted by a subcontractor who was determined to be qualified to submit a proposal in the trade or for the scope of work for which the subcontractor has submitted a proposal;
(b) Submitted by a subcontractor who attended the preproposal meeting; and
(c) Timely received by the construction manager at risk.
3. If a proposal does not satisfy the requirements of subsection 2, the construction manager at risk must return the proposal unopened to the subcontractor who submitted the proposal.

Notes

Nev. Admin. Code § 338.630
Added to NAC by Pub. Works Bd. by R099-11, eff. 5-30-2012

NRS 338.16995, 341.070, 341.110