Nev. Admin. Code § 477.840 - Certification of proper installation; metal placard required
1. Following the installation of a fire
standpipe system, the licensee shall submit a letter to the authority having
jurisdiction certifying that the system has been installed in accordance with
the plans approved by the authority having jurisdiction and all applicable
state and local codes.
2. Within 30
days after completing the installation or remodeling of a fire standpipe
system, the licensee shall attach a metal placard which must:
(a) Identify all requirements for the
hydraulic design.
(b) The number,
size and location of system outlets and the calculated discharge of the highest
outlet.