Nev. Admin. Code § 624.72514 - Order for corrective action: Determination of time permitted for compliance

In determining the time permitted for compliance with an order for corrective action issued pursuant to NRS 624.341, the Board or its designee will determine the time for compliance with the order by considering, without limitation:

1. The accepted industry practice regarding the performance of the work necessary to comply with the order for corrective action, in the climate or weather conditions of the area in which the construction project is located.
2. The number of days during which the owner of the construction project will make the site of the construction project available for the contractor to comply with the order for corrective action.
3. The time necessary to obtain materials required for the contractor to comply with the order for corrective action.

Notes

Nev. Admin. Code § 624.72514
Added to NAC by Contractors' Bd. by R022-04, eff. 4-30-2004; A by R014-19A, eff. 5/21/2020
NRS 624.100, 624.341, 624.361