Nev. Admin. Code § 704.8785 - Requirements for reporting data: Information relating to design, operations and safety; efficiency of generation of power

Current through March 28, 2022

A utility shall file with the Commission, in the format for a tariff, the requirements for:

1. The design, operations and safety related to cogeneration facilities and small power production facilities located within the utility's certificated area in this State; and
2. The total efficiency of the generation of power for each cogeneration facility located within the utility's certificated area in this State.

Notes

Nev. Admin. Code § 704.8785
Pub. Service Comm'n, Gen. Order 32 § 5.0, eff. 8-21-81-NAC A 3-27-92-Substituted in revision for NAC 704.720

NRS 703.025, 704.210