Nev. Admin. Code § 704.Sec. 14.1 - NEW
The affiliated utilities are not subject to the requirements of sections 2 to 14, inclusive after the earlier of:
1. The date on which the sum total of energy storage system resources approved by the Commission and procured by the affiliated utilities meets or exceeds 1,000 megawatts; or
2. December 31, 2030.