N.H. Admin. Code § Env-Dw 1105.03 - Management of Project Priority List
(a) A project on
the fundable portion of the project priority list shall be bypassed if the
project will not be ready to proceed during the funding year. Projects that
have been bypassed shall be placed in the contingency section and funded if the
project is ready to proceed when sufficient funds become available.
(b) The department shall review the project
priority list not less than monthly and update the list with any necessary
changes, such as revised loan award dates, revised estimated construction
assistance amounts, and project bypass.
(c) If additional funds become available
during the fiscal year, the department shall extend the fundable portion of the
priority list to include the highest ranked project in the contingency section
of the list.
(d) The department
shall remove a project from the project priority list if any of the following
is true:
(1) The project is fully funded from
other sources;
(2) The project is
found to be ineligible based on information received by the department
subsequent to the placement of the project on the list;
(3) The applicant informs the department in
writing that it does not intend to pursue financial assistance from the DWSRF;
or
(4) The applicant loses its
managerial or financial capability to construct and implement the
project.
Notes
(See Revision Note at chapter heading for Env-Dw 1100) #8702, eff 8-24-06