N.H. Admin. Code § Env-Dw 1107.03 - Categorical Exclusion (CE) Review
(a) The department
shall review the proposed project to determine whether the project qualifies
for a CE.
(b) A CE determination
shall be made if the project comprises only:
(1) Work on existing facilities where no new
disruption of the environment will occur, such as correction of leakage,
replacement of pipes in existing rights of way, or replacement or addition of
equipment or small new structures on an existing site;
(2) Work where only a small disturbance is
required to upgrade a facility, such as to install hydrants on existing water
mains; or
(3) Acquisition of land
for SWP purposes.
(c) If
the department determines that the project qualifies for a CE, the department
shall:
(1) Prepare a review document
describing the basis for its determination; and
(2) Forward the document to the New Hampshire
office of energy and planning (OEP) for the intergovernmental review process
and to the applicant to distribute for review and comment in accordance with
Env-Dw
1107.05.
(d) At the close of the review and comment
period, the department shall make a final determination in accordance with the
following:
(1) If no significant adverse
comments are received, the department shall issue a CE as the final action;
or
(2) If significant adverse
comments are received, the department shall prepare an EA in accordance with
Env-Dw
1107.04.
(e) The department shall send its final
determination in writing to the applicant and to any other person who requested
during the public comment period to receive a copy.