(a) The recipient
shall withhold 10% of all partial payments as retainage until 50% of the
project is complete.
(b) After the
project is 50% complete, no additional retainage shall be withheld from any
partial payments.
(c) Upon
substantial or final completion of the project, the recipient shall reduce the
retainage to 2%. The final 2% retainage shall be held during the one-year
warranty period and released only after the recipient has accepted the
project.