N.H. Admin. Code § Pas 305.02 - Application for Construction, Relocation, or Alteration in Length of Passenger Tramways
(a) Before the construction of any new
passenger tramway, relocation, or alteration in length of a passenger tramway,
the area operator shall submit to the board a profile of the lift line and a
plan showing proximity of power lines, structures, woods, highways, and rivers.
The plan and profile shall be submitted along with the appropriate application
as specified in (c) below, for the type of lift to be constructed, relocated,
or altered in length.
(b) The
operator shall not proceed with construction, relocation, or alteration in
length unless:
(1) He or she has received
approval from the board; or
(2) The
board has not responded within 30 days of receipt of the
application.
(c) Before
any passenger tramway construction, relocation, or alteration in length is
started, owners or area operators shall apply for the board's approval using
the application that correlates to the type of lift to be constructed,
relocated, or altered in length, as described in
Pas
305.03,
Pas
305.04 and
Pas
305.05.
Notes
#2297, eff 2-7-83; ss by #2704, eff 5-9-84, EXPIRED 5-9-90 (formerly Saf-S 1005.02)
New. #4862, eff 7-10-90; ss by #6020, eff 4-14-95; ss by #6284, eff 7-10-96; ss by #7800, eff 12-11-02, EXPIRED: 12-11-10
New. #10072, eff 1-11-12; amd by #10382, eff 7-23-13
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.