N.H. Admin. Code § Pas 306.01 - Initial Registration of a New Construction, Relocated, Altered in Length, or Modified Passenger Tramway
(a) Prior to
initial registration of a new construction, relocated, altered in length, or
modified passenger tramway, the following shall be completed and submitted to
the board:
(1) A stamped certificate from the
designer with original signatures that the lift meets all requirements set
forth by statute and these rules;
(2) The acceptance test and
inspection;
(3) A certified copy of
the results of a destruction test of the wire rope conducted by the
manufacturer or a laboratory;
(4)
The evacuation plans for an aerial lift; and
(5) Certification from a qualified engineer
that the lift conforms to the designer's plans, except for fiber rope
tows.
(b) Within 60
calendar days after the acceptance test, certified as-built plans shall be
completed and delivered to the owner and the tramway board.
Notes
#2297, eff 2-7-83; ss by #2704, eff 5-9-84, EXPIRED 5-9-90 (formerly Saf-S 1006.01)
New. #4862, eff 7-10-90; ss by #6284, eff 7-10-96; ss by #7800, eff 12-11-02, EXPIRED: 12-11-10
New. #10072, eff 1-11-12; amd by #10382, eff 7-23-13
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.