N.H. Admin. Code § Puc 805.02 - Excavation That Affects the Tolerance Zone
(a) Any person
conducting excavation activity that affects the tolerance zone surrounding an
underground facility shall exercise at all times such reasonable care as is
necessary to protect the underground facility from damage.
(b) Except as provided in (c) below, in order
to locate and identify an underground facility, the excavator shall excavate by
methods limited to:
(1) Hand
digging;
(2) Pot holing;
(3) Soft digging;
(4) Vacuum excavation;
(5) Other mechanical methods with the
approval of the underground facility owner or operator; or
(6) Other methods accepted in the industry
consistent with the alternatives listed in (1) through (5) above, which clearly
will not affect the integrity of the underground facility.
(c) For bituminous pavement and concrete
travel surface removal an excavator shall not be limited to hand digging and
the other non-invasive methods cited in (b) above.
(d) For parallel type excavations, such as
excavation along an existing underground facility at an approximately equal
distance when measured periodically, the excavator shall expose the existing
underground facility at intervals as often as necessary to avoid
damage.
(e) For perpendicular type
excavations in which the markings are completed in accordance with 806.01 (a)
(2), the excavator shall expose the existing underground facility using methods
listed in (b) above within the defined tolerance zone.
(f) In the event the excavator exposes what
appears to be the underground facility that is offset from the centerline:
(1) The excavator shall not assume there are
no other underground facilities having the same function within the tolerance
zone; and
(2) The excavator shall
continue using methods listed in (b) above through remainder of the tolerance
zone unless the verification of the existence or non-existence of underground
facilities is determined by the operator.
(g) For trenchless excavations, such as
horizontal drilling, boring, pneumatic jacking, tunneling, and pavement
reclamation, reasonable care for purposes of
Puc
805.02(a) shall include determining
the exact depth of the underground facility and clearances required by the
operator and incorporating location details into the trenchless excavation
procedure so as to avoid any potential damage of the underground
facility.
Notes
#5616, eff 4-20-93, EXPIRED: 4-20-99
New. #7259, INTERIM, eff 5-2-00, EXPIRES: 8-30-00; ss by #7350, eff 8-23-00; ss by #7900, eff 5-29-03; ss by #9318, eff 11-8-08
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.