N.H. Admin. Code § Puc 904.06 - Upgrades or Changes in the Net Metering Facility
(a) The customer-generator shall provide to the distribution utility a written update regarding any of the information required to be provided in the interconnection application as any such changes occur.
(b) The customer-generator shall re-certify to the distribution utility the applicable certifications required by Puc 904.05(c) and (d), if any of the following occurs:
(1) The generation capacity of the facility is increased or its source is changed;
(2) Any key component of the facility, such as the inverter, is replaced or upgraded; or
(3) The relays for a non-inverter facility are replaced, rewired, or upgraded.
Notes
#7424, eff 1-12-01; ss by #9353, INTERIM, eff 1-12-09, EXPIRED: 7-11-09
New. #9515, eff 7-18-09 (from Puc 904.05); ss by #9998, eff 9-20-11
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.