N.H. Admin. Code § Puc 908.03 - Distribution Utility Access to Net-Metered Facility
(a) The distribution utility may inspect the net-metered facility at its own expense at a time mutually agreeable to the customer-generator upon reasonable notice to the customer-generator.
(b) Except in emergency circumstances, the distribution utility shall provide not less than 5 business days' prior notice to the customer-generator to enter the facility site in order to inspect the net-metered facility, install additional controls or meters, or conduct additional tests.
(c) A customer-generator shall not deny access to the distribution utility to inspect the net metered system, install additional controls or meters or conduct additional tests.
Notes
#7424, eff 1-12-01; ss by #9353, INTERIM, eff 1-12-09, EXPIRED: 7-11-09
New. #9515, eff 7-18-09; ss by #9998, eff 9-20-11