N.H. Admin. Code § Site 301.04 - Financial, Technical and Managerial Capability
Each application shall include a detailed description of the applicant's financial, technical, and managerial capability to construct and operate the proposed energy facility, as follows:
(a) Financial information shall include:
(1) A description of the applicant's
experience financing other energy facilities;
(2) A description of the corporate structure
of the applicant, including a chart showing the direct and indirect ownership
of the applicant;
(3) A description
of the applicant's financing plan for the proposed facility, including the
amounts and sources of funds required for the construction and operation of the
proposed facility;
(4) An
explanation of how the applicant's financing plan compares with financing plans
employed by the applicant or its affiliates, or, if no such plans have been
employed by the applicant or its affiliates, then by unaffiliated project
developers if and to the extent such information is publicly available, for
energy facilities that are similar in size and type to the proposed facility,
including any increased risks or costs associated with the applicant's
financing plan; and
(5) Current and
pro forma statements of assets and liabilities of the applicant;
(b) Technical information shall
include:
(1) A description of the applicant's
qualifications and experience in constructing and operating energy facilities,
including projects similar to the proposed facility; and
(2) A description of the experience and
qualifications of any contractors or consultants engaged or to be engaged by
the applicant to provide technical support for the construction and operation
of the proposed facility, if known at the time of application;
(c) Managerial information shall
include:
(1) A description of the applicant's
management structure for the construction and operation of the proposed
facility, including an organizational chart for the applicant;
(2) A description of the qualifications of
the applicant and its executive personnel to manage the construction and
operation of the proposed facility; and
(3) To the extent the applicant plans to rely
on contractors or consultants for the construction and operation of the
proposed facility, a description of the experience and qualifications of the
contractors and consultants, if known at the time of application.