N.H. Admin. Code § Site 301.08 - Effects on Public Health and Safety
Each application shall include the following information regarding the effects of, and plans for avoiding, minimizing, or mitigating potential adverse effects of, the proposed energy facility on public health and safety:
(a) For proposed wind energy
systems:
(1) A sound impact assessment
prepared in accordance with professional standards by an expert in the field,
which assessment shall include the reports of a preconstruction sound
background study and a sound modeling study, as specified in
Site
301.18;
(2) An assessment that identifies the
astronomical maximum as well as the anticipated hours per year of shadow
flicker expected to be perceived at each residence, learning space, workplace,
health care setting, outdoor or indoor public gathering area, other occupied
building, and roadway, within a minimum of 1 mile of any turbine, based on
shadow flicker modeling that assumes an impact distance of at least 1 mile from
each of the turbines;
(3)
Description of planned setbacks that indicate the distance between each wind
turbine and the nearest landowner's existing building and property line, and
between each wind turbine and the nearest public road and overhead or
underground energy infrastructure or energy transmission pipeline within 2
miles of such wind turbine, and explain why the indicated distances are
adequate to protect the public from risks associated with the operation of the
proposed wind energy facility;
(4)
An assessment of the risks of ice throw, blade shear, and tower collapse on
public safety, including a description of the measures taken or planned to
avoid or minimize the occurrence of such events, if necessary, and the
alternative measures considered but rejected by the applicant;
(5) Description of the lightning protection
system planned for the proposed facility;
(6) Description of any determination made by
the Federal Aviation Administration regarding whether any hazard to aviation is
expected from any of the wind turbines included in the proposed facility, and
describe the Federal Aviation Administration's lighting, turbine color, and
other requirements for the wind turbines;
(7) A decommissioning plan prepared by an
independent, qualified person with demonstrated knowledge and experience in
wind generation projects and cost estimates, which plan shall provide for
removal of all structures and restoration of the facility site;
(8) The decommissioning plan required under
(7) above shall include each of the following:
a. A description of sufficient and secure
funding to implement the plan, which shall not account for the anticipated
salvage value of facility components or materials;
b. The provision of financial assurance in
the form of an irrevocable standby letter of credit, performance bond, surety
bond, or unconditional payment guaranty executed by a parent company of the
facility owner maintaining at all times an investment grade credit
rating;
c. All turbines, including
the blades, nacelles and towers, shall be disassembled and transported
off-site;
d. All transformers shall
be transported off-site;
e. The
overhead power collection conductors and the power poles shall be removed from
the site;
f. All underground
infrastructure at depths less than four feet below grade shall be removed from
the site and all underground infrastructure at depths greater than four feet
below finished grade shall be abandoned in place; and
g. Areas where subsurface components are
removed shall be filled, graded to match adjacent contours, reseeded,
stabilized with an appropriate seed and allowed to re-vegetate
naturally;
(9) A plan
for fire protection for the proposed facility prepared by or in consultation
with a fire safety expert; and
(10)
An assessment of the risks that the proposed facility will interfere with the
weather radars used for severe storm warning or any local weather
radars.
(b) For electric
transmission facilities, an assessment of electric and magnetic fields
generated by the proposed facility and the potential impacts of such fields on
public health and safety, based on established scientific knowledge, and an
assessment of the risks of collapse of the towers, poles, or other supporting
structures, and the potential adverse effects of any such collapse.
(c) For high pressure gas pipelines:
(1) A comprehensive health impact assessment
prepared by an independent health and safety expert in accordance with
nationally recognized standards, and specifically designed to identify and
evaluate potential short-term and long-termhuman health impacts by identifying
potential pathways for facility-related contaminants to harm human health,
quantifying the cumulative risks posed by any contaminants, and recommending
necessary avoidance, minimization, or mitigation;
(2) A sound and vibration impact assessment
prepared by an independent expert in the field, in accordance with ANSI/ASA
S12.9-2013 Part 3 for short-term monitoring and with ANSI S12.9-1992 2013 Part
2 for long-term monitoring, including the reports of a preconstruction sound
and vibration background study and a sound and vibration modeling
study;
(3) A description of planned
setbacks that indicate the distance between:
a. The proposed high pressure gaspipeline and
existing buildings on, and the boundaries of, abutting properties;
b. Any associated compressor station and
schools, day-care centers, health care facilities, residences, residential
neighborhoods, places of worship, elderly care facilities, and farms within a
one mile radius; and
c. The
proposed high pressure gaspipeline and any overhead or underground electric
transmission line within 1/2 mile;
(4) An explanation of why the setbacks
described by the applicant in response to (3), above, are adequate to protect
the public from risks associated with the operation of the high pressure gas
pipeline; and
(5) A description of
all permanently installed exterior lighting at compressor stations and how it
complies with Site
301.14(f)(5)c.
(d) For all energy facilities:
(1) Except as otherwise provided in (a)(1)
above, an assessment of operational sound associated with the proposed
facility, if the facility would involve use of equipment that might reasonably
be expected to increase sound by 10 decibel A-weighted (dBA) or more over
background levels, measured at the L-90 sound level, at the property boundary
of the proposed facility site or, in the case of an electric transmission line
or an energy transmission pipeline, at the edge of the right-of-way or the edge
of the property boundary if the proposed facility, or portion thereof, will be
located on land owned, leased or otherwise controlled by the applicant or an
affiliate of the applicant;
(2) A
facility decommissioning plan prepared by an independent, qualified person with
demonstrated knowledge and experience in similar energy facility projects and
cost estimates; the decommissioning plan shall include each of the following:
a. A description of sufficient and secure
funding to implement the plan, which shall not account for the anticipated
salvage value of facility components or materials;
b. The provision of financial assurance in
the form of an irrevocable standby letter of credit, performance bond, surety
bond, or unconditional payment guaranty executed by a parent company of the
facility owner maintaining at all times an investment grade credit
rating;
c. All transformers shall
be transported off-site; and
d. All
underground infrastructure at depths less than four feet below grade shall be
removed from the site and all underground infrastructure at depths greater than
four feet below finished grade shall be abandoned in place;
(3) A plan for fire safety
prepared by or in consultation with a fire safety expert;
(4) A plan for emergency response to the
proposed facility site; and
(5) A
description of any additional measures taken or planned to avoid, minimize, or
mitigate public health and safety impacts that would result from the
construction and operation of the proposed facility, and the alternative
measures considered but rejected by the applicant.