N.H. Admin. Code § Site 301.12 - Timeframe for Application Review
(a)
Pursuant to RSA
162-H:7, VI-b, each state agency having
permitting or other regulatory authority over the proposed energy facility
shall report its progress to the committee within 150 days after application
acceptance, outlining draft permit conditions and specifying additional data
requirements necessary to make a final decision on the parts of the application
that relate to its permitting or other regulatory authority.
(b) Pursuant to
RSA
162-H:7, VI-c, each state agency having
permitting or other regulatory authority over the proposed energy facility
shall make and submit to the committee a final decision on the parts of the
application that relate to its permitting and other regulatory authority, no
later than 240 days after application acceptance.
(c) Pursuant to
RSA
162-H:7, VI-d, the committee shall issue or
deny a certificate for an energy facility within 365 days after application
acceptance.
(d) Pursuant to
RSA
162-H:14, I, the committee shall temporarily
suspend its deliberations and the time frames set forth in this section at any
time while an application is pending before the committee, if it finds that
such suspension is in the public interest.