N.H. Admin. Code § Site 301.13 - Criteria Relative to Findings of Financial, Technical, and Managerial Capability
(a) In determining
whether an applicant has the financial capability to construct and operate the
proposed energy facility, the committee shall consider:
(1) The applicant's experience in securing
funding to construct and operate energy facilities similar to the proposed
facility;
(2) The experience and
expertise of the applicant and its advisors, to the extent the applicant is
relying on advisors;
(3) The
applicant's statements of current and pro forma assets and liabilities;
and
(4) Financial commitments the
applicant has obtained or made in support of the construction and operation of
the proposed facility.
(b) In determining whether an applicant has
the technical capability to construct and operate the proposed facility, the
committee shall consider:
(1) The applicant's
experience in designing, constructing, and operating energy facilities similar
to the proposed facility; and
(2)
The experience and expertise of any contractors or consultants engaged or to be
engaged by the applicant to provide technical support for the construction and
operation of the proposed facility, if known at the time.
(c) In determining whether an applicant has
the managerial capability to construct and operate the proposed facility, the
committee shall consider:
(1) The applicant's
experience in managing the construction and operation of energy facilities
similar to the proposed facility; and
(2) The experience and expertise of any
contractors or consultants engaged or to be engaged by the applicant to provide
managerial support for the construction and operation of the proposed facility,
if known at the time.