N.H. Admin. Code § Site 301.17 - Conditions of Certificate
In determining whether a certificate shall be issued for a proposed energy facility, the committee shall consider whether the following conditions should be included in the certificate in order to meet the objectives of RSA 162-H:
(a) A
requirement that the certificate holder promptly notify the committee of any
proposed or actual change in the ownership or ownership structure of the holder
or its affiliated entities and request approval of the committee of such
change;
(b) A requirement that the
certificate holder promptly notify the committee of any proposed or actual
material change in the location, configuration, design, specifications,
construction, operation, or equipment components of the energy facility subject
to the certificate and request approval of the committee of such
change;
(c) A requirement that the
certificate holder continue consultations with the New Hampshire division of
historical resources of the department of cultural resources and, if
applicable, the federal lead agency, and comply with any agreement or
memorandum of understanding entered into with the New Hampshire division of
historical resources of the department of cultural resources and, if
applicable, the federal lead agency;
(d) Delegation to the administrator or
another state agency or official of the authority to monitor the construction
or operation of the energy facility subject to the certificate and to ensure
that related terms and conditions of the certificate are met;
(e) Delegation to the administrator or
another state agency or official of the authority to specify the use of any
technique, methodology, practice, or procedure approved by the committee within
the certificate and with respect to any permit, license, or approval issued by
a state agency having permitting or other regulatory authority;
(f) Delegation to the administrator or
another state agency or official of the authority to specify minor changes in
route alignment to the extent that such changes are authorized by the
certificate for those portions of a proposed electric transmission line or
energy transmission pipeline for which information was unavailable due to
conditions which could not have been reasonably anticipated prior to the
issuance of the certificate;
(g) A
requirement that the energy facility be sited subject to setbacks or operate
with designated safety zones in order to avoid, mitigate, or minimize potential
adverse effects on public health and safety;
(h) Other conditions necessary to ensure
construction and operation of the energy facility subject to the certificate in
conformance with the specifications of the application; and
(i) Any other conditions necessary to serve
the objectives of RSA 162-H or to support findings made pursuant to
RSA
162-H:16.