N.H. Code Admin. R. Puc 2505.03 - Preliminary Designation

(a) A developer of a proposed new or repowered source may request preliminary designation as an eligible source by submitting the information described in Puc 2505.02, provided that any tentative or estimated information, such as the initial commercial operation date, is so identified.
(b) The commission shall rule on a request for preliminary designation within 60 days of receiving all the required information. The commission shall grant the request for preliminary designation when the facts provided demonstrate that the planned facility is expected to meet the requirements of the requested class. When granting such a request, the commission shall attach such conditions to its approval as are reasonably necessary to ensure compliance with RSA 362-F and this chapter. When denying such a request, the commission shall provide a detailed explanation of the basis for its decision.
(c) Preliminary designation under this section shall not exempt a facility from the regular application requirements of this part. A facility granted preliminary designation of eligibility shall be entitled to full certification, provided that the facility as constructed or modified is consistent with the facts as stated in the request for preliminary designation and complies with any conditions added by the commission.

Notes

N.H. Code Admin. R. Puc 2505.03

#9037, INTERIM, eff 11-27-07, EXPIRED: 5-25-08

New. #9169, eff 6-3-08; ss by #10741, eff 12-5-14

Amended by Volume XXXVIII Number 06, Filed February 8, 2018, Proposed by #12473, Effective 2/1/2018, Expires 2/1/2028.