N.H. Code Admin. R. Puc 901.02 - Applicability

(a) Puc 904 through Puc 908 shall be applicable only to small net-metering customers.
(b) Puc 903.02(l) through (p) shall only apply to net surplus electricity exported to the distribution system that accumulates during the 12 monthly billing cycles preceding the March 2012 billing cycle and in subsequent billing cycles.
(c) Where expressly noted, the provisions of Puc 900 shall apply only to customer-generators subject to the standard net metering tariff or only to customer-generators subject to the alternative net metering tariff.
(d) Interconnection of large net-metering customer-generators shall be governed by each utility's interconnection practices as set forth in its tariff filed with the commission.
(e) With the exception of Puc 903.02(u) and Puc 905.07, and unless otherwise noted, Puc 900 shall be applicable to rural electric cooperatives for which a certificate of deregulation is on file with the commission with respect to customer-generator subject to the standard net metering tariff up to the applicable cap set forth in Puc 903.02(b).

Notes

N.H. Code Admin. R. Puc 901.02

#9998, eff 9-20-11

Amended by Volume XL Number 33, Filed August 13, 2020, Proposed by #13080, Effective 9/14/2020, Expires 9/14/2030

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.