N.H. Code Admin. R. Puc 908.03 - Distribution Utility Access to Net-Metered Facility

(a) The distribution utility may inspect the net-metered facility at its own expense at a time mutually agreeable to the customer-generator upon reasonable notice to the customer-generator.
(b) Except in emergency circumstances, the distribution utility shall provide not less than 5 business days' prior notice to the customer-generator to enter the facility site in order to inspect the net-metered facility, install additional controls or meters, or conduct additional tests.
(c) A customer-generator shall not deny access to the distribution utility to inspect the net metered system, install additional controls or meters or conduct additional tests.

Notes

N.H. Code Admin. R. Puc 908.03

#7424, eff 1-12-01; ss by #9353, INTERIM, eff 1-12-09, EXPIRED: 7-11-09

New. #9515, eff 7-18-09; ss by #9998, eff 9-20-11

Amended by Volume XL Number 33, Filed August 13, 2020, Proposed by #13080, Effective 9/14/2020, Expires 9/14/2030