N.J. Admin. Code § 14:2-3.1 - Notice of intent to excavate-timing
(a) A person shall
not perform excavation or demolition, as defined at
N.J.A.C.
14:2-1.2, unless the person performing the
excavation or demolition, or a responsible contractor, has provided notice of
the excavation or demolition to the One-Call center by dialing 811 in New
Jersey, out-of-State, 1800-272-1000, or by electronic notice as directed by the
One-Call System operator in accordance with its Board-approved tariff. Requests
provided electronically or through any procedure other than that directed for
use by the One-Call System operator shall not constitute notice in compliance
with this section.
(b) An excavator
or responsible contractor, as defined at
N.J.A.C.
14:2-1.2, shall notify the One-Call center of
the intent to engage in any excavation or demolition not less than three
business days before beginning the excavation or demolition, and not more than
10 business days prior to beginning the excavation or demolition, except if the
excavation or demolition is necessary because of an emergency, as defined at
N.J.A.C.
14:2-1.2. An excavator that performs
emergency excavation or demolition shall comply with the notice requirements at
N.J.A.C.
14:2-3.6.
(c) Notice provided in accordance with (a)
above, for an excavation or demolition that is commenced within 10 business
days after the notice, shall remain valid for 45 business days from the
notification, provided that the excavator maintains the markout that is made by
an operator. Any excavation or demolition continuing after the 45 business days
shall require a new notification that meets the requirements at (a)
above.
(d) If the excavation or
demolition is not commenced within 10 business days after notice is provided to
the One-Call center in accordance with (a) above:
1. The notice shall no longer be
valid;
2. The excavator shall not
perform any excavation or demolition on the site until the excavator or
responsible contractor submits a new notification to the One-Call center;
and
3. The new notification shall
comply with (a) above in all respects; that is, the excavator shall notify the
One-Call center at least three business days before, but no more than 10
business days before, beginning the excavation or demolition.
(e) By providing notice to the
One-Call center, an excavator or responsible contractor assumes responsibility
and liability for ensuring that the excavation or demolition is performed in
accordance with this chapter and other applicable law.
(f) An excavation that is undertaken in order
to repair or replace the vent or filler pipe of an underground heating oil tank
or a heating system shall not be subject to the three-business-day advance
notice requirement at (a) above, provided it meets all of the requirements at
(f)1, 2, and 3 below. Instead, such an excavation may be started immediately
after notice to the One-Call center.
1. The
excavation is undertaken in response to a service call by a customer;
2. The excavation or demolition uses only
non-mechanized equipment; and
3.
The excavation begins after October 1 and ends before April 30 of the following
year.
(g) A routine
excavation that is undertaken for pest management purposes on residential
property shall be subject to the three-business day advance notice requirement
under (a) above, the first time the excavation is performed. However, the
excavation may be performed a second and subsequent times without notice to the
One-Call center, provided that all of the following requirements are met:
1. The excavation is performed every time by
the same excavator that provided notice to the One-Call center;
2. The excavation shall be the same type of
work, shall be within the extent of work and within the depth field set forth
in the original notice to the One-Call center;
3. The excavation meets the definition of
"routine"; and
4. The excavation is
performed solely for pest management purposes.
Notes
See: 33 N.J.R. 2606(a), 34 N.J.R. 1458(a).
Added a new (a), recodified former (a) through (d) as (b) through (e) and amended paragraph designators throughout, and added (f).
Recodified in part from N.J.A.C. 14:2-4.1 and amended by R.2007 d.298, effective
See: 39 N.J.R. 1232(a), 39 N.J.R. 4422(b).
Section was "Notice". Rewrote the section. Former N.J.A.C. 14:2-3.1, Designation, recodified to N.J.A.C. 14:2-2.2.
Amended by R.2009 d.250, effective
See: 40 N.J.R. 6928(a), 41 N.J.R. 3096(a).
Added (g).
Administrative correction.
See: 41 N.J.R. 3939(a).