N.J. Admin. Code § 14:2-3.5 - Excavation or demolition in response to an emergency
(a) If an
excavator undertakes an excavation or demolition in response to an emergency
that does not permit compliance by the excavator with the notification
requirements of
N.J.A.C.
14:2-3.1, the excavator shall comply with
this section.
(b) An excavator that
is subject to this section shall notify the One-Call center of an emergency
excavation or demolition as soon as reasonably possible without causing a delay
in addressing the emergency, and shall include in the notice a description of
the nature of the emergency and provide contact information of a person
knowledgeable of the excavation to be performed.
(c) In a case where the excavator must
perform excavation or demolition in order to address the emergency, the notice
to the One-Call center shall also include a brief explanation of the
circumstances that prevented the excavator from providing notice in accordance
with
N.J.A.C.
14:2-3.1.
(d) An excavator that performs excavation or
demolition in response to an emergency shall take all reasonable precautions to
protect any underground facilities that may be located at the site of the
excavation or demolition.
(e) If an
excavation is undertaken in order to repair or replace the vent or filler pipe
of an underground heating oil tank or a heating system, the excavation may be
started immediately after notice has been given to the One-Call center,
provided the excavation meets all of the requirements at (e)1 through 3 below:
1. The excavation is undertaken in response
to a service call by a customer;
2.
The excavation or demolition uses only non-mechanized equipment; and
3. The excavation begins after October 1 and
ends before April 30 of the following year.
(f) An excavation performed in accordance
with (e) above shall meet all other requirements of this section and this
chapter.
(g) Emergency
notifications shall only be valid for the period that the conditions defined at
N.J.A.C.
14:2-1.2 exist. If a temporary repair is made
and requires additional excavation, a routine markout request is
required.
Notes
See: 39 N.J.R. 1232(a), 39 N.J.R. 4422(b).