N.J. Admin. Code § 14:8-5.2 - General interconnection provisions
(a) Each EDC
shall provide the following three review procedures for applications for
interconnection of customer-generator facilities:
1. Level 1: An EDC shall use this review
procedure for all applications to connect inverter-based customer-generator
facilities, which have a power rating of 10 kW or less, and which meet the
certification requirements at
14:8-5.3. Level 1 interconnection
review procedures are set forth at
14:8-5.4;
2. Level 2: An EDC shall use this review
procedure for applications to connect customer-generator facilities with a
power rating of two MW or less, which meet the certification requirements at
14:8-5.3. Level 2 interconnection
review procedures are set forth at
14:8-5.5; and
3. Level 3: An EDC shall use this review
procedure for applications to connect customer-generator facilities that do not
qualify for either the level 1 or level 2 interconnection review procedures.
Level 3 interconnection review procedures are set forth at
14:8-5.6.
(b) Each EDC shall designate an employee or
office from which an applicant can obtain basic application forms and
information through an informal process. On request, this employee or office
shall provide all relevant forms, documents, and technical requirements for
submittal of a complete application for interconnection review under this
section, as well as specific information necessary to contact the EDC
representatives assigned to review the application.
(c) Upon request, the EDC shall meet with an
applicant who qualifies for level 2 or level 3 interconnection review, to
assist them in preparing the application.
(d) An application for interconnection review
shall be submitted on a standard form, available from the EDC. The application
form will require the following types of information:
1. Basic information regarding the
customer-generator and the electricity supplier(s) involved;
2. Information regarding the type and
specifications of the customer-generator facility;
3. Information regarding the contractor who
will install the customer-generator facility;
4. Certifications and agreements regarding
utility access to the customer-generator's property, emergency procedures,
liability, compliance with electrical codes, proper operation and maintenance,
receipt of basic information; and
5. Other similar information as needed to
determine the compliance of a particular applicant with this chapter.
(e) An EDC shall not be
responsible for the cost of determining the rating of equipment owned by a
customer-generator, or of equipment owned by other local customers.
(f) An EDC shall not require a
customer-generator whose facility meets the criteria for interconnection
approval under the level 1 or level 2 interconnection review procedure at
14:8-5.4 and 5.5 to install
additional controls or external disconnect switches not included in the
interconnection equipment, to perform or pay for additional tests or to
purchase additional liability insurance, except if agreed to by the
applicant.
(g) If the
interconnection of a customer-generator facility is subject to interconnection
requirements of FERC or PJM, the provisions of this subchapter that apply to
interconnection apply to that facility only to the extent that they do not
conflict with the interconnection requirements of FERC or PJM.
(h) If an applicant for interconnection
disagrees with an EDC's determination of fact or need regarding matters covered
in this subchapter, or if any person has a complaint regarding matters covered
in this subchapter, the applicant or other person may file an informal
complaint with the Board under
14:1-5.1 3, or may file a petition
with the Board under N.J.A.C. 14:1-5.
(i) Once a customer-generator has met the
level 1 interconnection requirements at
14:8-5.4, or has met the level 2
interconnection requirements at
14:8-5.5, the EDC shall notify the
customer-generator in writing that the customer-generator is authorized to
energize the customer-generator facility, as follows:
1. The EDC shall send the authorization to
the e-mail address, and to the U.S. Postal Service mailing address that is
listed on the customer-generator's submitted interconnection application form;
and
2. The EDC shall not condition
the authorization to energize on the EDC's replacement of the
customer-generator's meter.
(j) The applicant shall not operate the
customer-generator facility until the EDC's application and inspection process
is completed. Unauthorized system interconnection and operation will result in
no payment for excess generation credits.
Notes
See: 41 N.J.R. 2215(a), 42 N.J.R. 78(a).
In (a), updated the N.J.A.C. references throughout; in (a)3, substituted "that" for "with a power rating of two MW or less, which"; in the introductory paragraph of (d), deleted "and posted on the Board's website at www.bpu.state.nj.us" following "EDC"; and reserved (f). Former N.J.A.C. 14:8-5.2, Purpose and scope, recodified to N.J.A.C. 14:8-7.2.
Amended by R.2012 d.107, effective
See: 43 N.J.R. 1162(a), 44 N.J.R. 1703(a).
In (d)1, substituted "customer-generator" for "applicant"; and added (f) and (i).
Amended by R.2013 d.066, effective
See: 44 N.J.R. 2043(a), 45 N.J.R. 942(a).
Added (j).
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.