N.J. Admin. Code § 14:8-5.5 - Level 2 interconnection review
(a) Each EDC shall
adopt a level 2 interconnection review procedure. The EDC shall use the level 2
interconnection review procedure for an application to interconnect a
customer-generator facility that meets both of the following criteria:
1. The facility has a capacity of two
megawatts or less; and
2. The
facility has been certified in accordance with
N.J.A.C. 14:8-5.3.
(b) For a customer-generator facility
described at (a) above, the EDC shall approve interconnection under the level 2
interconnection review procedure if all of the applicable requirements at (c)
through (l) below are met. An EDC shall not impose additional
requirements not specifically authorized under this section.
(c) The aggregate generation capacity on the
line section to which the customer-generator facility will interconnect,
including the capacity of the customer-generator facility, shall not cause any
distribution protective equipment (including, but not limited to, substation
breakers, fuse cutouts and line reclosers) or customer equipment on the
electric distribution system, to exceed 90 percent of the short circuit
interrupting capability of the equipment. In addition, a customer-generator
facility shall not be connected to a circuit that already exceeds 90 percent of
the short circuit interrupting capability, prior to interconnection of the
facility.
(d) If there are posted
transient stability limits to generating units located in the general
electrical vicinity of the proposed point of common coupling (for example,
within three or four transmission voltage level busses), the aggregate
generation capacity (including the customer-generator facility) connected to
the distribution low voltage side of the substation transformer feeding the
line section containing the point of common coupling shall not exceed 10
MW.
(e) The aggregate generation
capacity connected to the line section , including the customer-generator
facility, shall not contribute more than 10 percent to the line section 's
maximum fault current at the point on the high voltage (primary) level nearest
the proposed point of common coupling .
(f) If a customer-generator facility is to be
connected to a radial line section , the aggregate generation capacity connected
to the electric distribution system by non-EDC sources, including the
customer-generator facility, shall not exceed 10 percent (or 15 percent for
solar electric generation ) of the total circuit annual peak load. For the
purposes of this subsection, annual peak load shall be based on measurements
taken over the 12 months prior to the submittal of the application, measured at
the substation nearest to the customer-generator facility.
(g) If a customer-generator facility is to be
connected to three-phase, three wire primary EDC distribution lines, a
three-phase or single-phase generator shall be connected
phase-to-phase.
(h) If a
customer-generator facility is to be connected to three-phase, four wire
primary EDC distribution lines, a three-phase or single phase generator shall
be connected line-to-neutral and shall be effectively grounded.
(i) If a customer-generator facility is to be
connected to a single-phase shared secondary, the aggregate generation capacity
on the shared secondary, including the customer-generator facility, shall not
exceed 20 kilovolt-amps (kVA).
(j)
If a customer-generator facility is single-phase and is to be connected to a
transformer center tap neutral of a 240 volt service, the addition of the
customer-generator facility shall not create an imbalance between the two sides
of the 240 volt service, which is greater than 20 percent of the nameplate
rating of the service transformer.
(k) A customer-generator facility's point of
common coupling shall not be on a transmission line.
(l) If a customer-generator
facility's proposed point of common coupling is on a spot or area network , the
interconnection shall meet all of the following requirements that apply, in
addition to the requirements in (c) through (k) above:
1. For a customer-generator facility that
will be connected to a spot network circuit, the aggregate generation capacity
connected to that spot network from customer-generator facilities, including
the customer-generator facility, shall not exceed five percent of the spot
network 's maximum load;
2. For a
customer-generator facility that utilizes inverter based protective functions,
which will be connected to an area network , the customer-generator facility,
combined with other exporting customer-generator facilities on the load side of
network protective devices, shall not exceed 10 percent of the minimum annual
load on the network, or 500 kW, whichever is less. For the purposes of this
paragraph, the percent of minimum load for solar electric generation
customer-generator facility shall be calculated based on the minimum load
occurring during an off-peak daylight period; and/or
3. For a customer-generator facility that
will be connected to a spot or an area network that does not utilize inverter
based protective functions, or for an inverter based customer-generator
facility that does not meet the requirements of (l)1 or 2
above, the customer-generator facility shall utilize reverse power relays or
other protection devices that ensure no export of power from the
customer-generator facility, including inadvertent export (under fault
conditions) that could adversely affect protective devices on the
network.
(m) An
applicant shall submit an Interconnection Application/Agreement Form for level
2 interconnection review. The standard form is available from the EDC , and
includes a Part 1 (Terms and Conditions) and a Part 2 (Certificate of
Completion).
(n) Within three
business days after receiving an application for level 2 interconnection
review, the EDC shall provide written or e-mail notice to the applicant that it
received the application and whether the application is complete. If the
application is incomplete, the written notice shall include a list of all of
the information needed to complete the application.
(o) Within 15 business days
after the EDC notifies the applicant that the application is complete under (n)
above, the EDC shall notify the applicant by e-mail or in writing of one of the
determinations at (o)1 through 4 below, as applicable. During
the 15 business days provided under this subsection, the EDC may, at its own
expense, conduct any studies or tests it deems necessary to evaluate the
proposed interconnection and arrive at one of the following determinations:
1. The customer-generator facility meets the
applicable requirements in (c) through (l) above. In this
case, the EDC shall:
i. Notify the applicant ,
by e-mail or other writing, that the interconnection will be finally approved
upon completion of the process set forth at (p) through (r) below;
and
ii. Within three business days
after the notice in (o)1i above, the EDC shall return to the
applicant Part 1 of the original application, signed by the appropriate EDC
representative;
2. The
customer-generator facility has failed to meet one or more of the applicable
requirements at (c) through (l) above, but the EDC has
nevertheless determined that the customer-generator facility can be
interconnected consistent with safety, reliability and power quality. In this
case, the EDC shall:
i. Notify the applicant
by e-mail or other writing that the interconnection will be finally approved
upon completion of the process set forth at (p) through (r) below;
and
ii. Within five business days
after the notice in (o)2i above, the EDC shall return to the
applicant Part 1 of the original application, signed by the appropriate EDC
representative;
3. The
customer-generator facility has failed to meet one or more of the applicable
requirements at (c) through (l) above, but the initial review
indicates that additional review may enable the EDC to determine that the
customer-generator facility can be interconnected consistent with safety,
reliability and power quality. In such a case, the EDC shall:
i. Notify the customer-generator of, and
offer to perform, additional review to determine whether minor modifications to
the electric distribution system (for example, changing meters, fuses or relay
settings) would enable the interconnection to be made consistent with safety,
reliability and power quality. The EDC notice shall provide to the applicant a
nonbinding, good faith estimate of the costs of such additional review, and/or
such minor modifications;
ii. If
the customer-generator notifies the EDC that the customer-generator consents to
pay for the review and/or modifications, the EDC shall undertake the review or
modifications within 15 business days after this notice from the
customer-generator; and
iii. Within
15 business days after the review or modifications are complete, the EDC shall
return to the customer-generator Part 1 of the original application, signed by
the appropriate EDC representative; or
4. The customer-generator facility has failed
to meet one or more of the applicable requirements at (c) through
(l) above, and the initial review indicates that additional
review would not enable the EDC to determine that the customer-generator
facility could be interconnected consistent with safety, reliability and power
quality. In such a case, the EDC shall:
i.
Notify the customer-generator in writing that the interconnection application
has been denied; and
ii. Provide a
written explanation of the reason(s) for the denial, including a list of
additional information and/or modifications to the customer-generator's
facility, which would be required in order to obtain an approval under level 2
interconnection procedures.
(p) Once a customer-generator receives Part 1
of the application with the EDC signature in accordance with
(o)1, 2 or 3 above, and has installed and interconnected the
customer-generator facility to the EDC 's distribution system, the
customer-generator shall obtain approval of the facility from the appropriate
construction official, as defined at
N.J.A.C. 5:23-1.4.
(q) At least 10 business days prior to
starting operation of the customer-generator facility (unless the EDC does not
require 10 days notice), the customer-generator shall:
1. Provide the EDC with documentation that
the interconnection has been approved by the appropriate construction
official;
2. Submit Part 2 of the
application, signed by the customer-generator; and
3. Indicate to the EDC the anticipated start
date for operation of the customer-generator facility.
(r) The EDC may require an EDC inspection of
a customer-generator facility prior to operation, and may require and arrange
for witness of commissioning tests as set forth in IEEE standard 1547
(published July 2003) in accordance with the following:
1. The customer-generator shall submit the
construction official's approval and the signed Part 2 under (q) above and
inform the EDC that the customer-generator facility is ready for EDC
inspection;
2. Within five business
days after the customer-generator informs the EDC under (r)1 above that the
customer-generator facility is ready for inspection, the EDC shall notify the
customer-generator of three or more available four-hour inspection appointments
(for example, February 4th from noon to 4:00 P.M., February 6th from 10:00 A.M.
to 2:00 P.M., or February 7th from 1:00 P.M. to 5:00 P.M.);
3. The appointments offered under (r)2 above
shall be no later than 15 business days after the EDC offers the appointments,
(that is, within 20 business days after the customer-generator submittal under
(r)1 above);
4. The
customer-generator shall notify the EDC which of the offered inspection
appointments the customer-generator prefers or shall arrange another time by
mutual agreement with the EDC ;
5.
Within five business days after successful completion of the EDC inspection,
the EDC shall notify the customer-generator that it is authorized to energize
the facility. The notice shall be provided in the format required under
N.J.A.C. 14:8-5.2(i);
and
6. The applicant shall not
begin operating the customer-generator facility until after the inspection and
testing is completed.
(s) If an application for level 2
interconnection review fails to meet the requirements as described at
(o)3 or 4 above, or is denied because it does not meet one or
more of the requirements in this section, the applicant may resubmit the
application under the level 3 interconnection review procedure.
Notes
See: 41 N.J.R. 2215(a), 42 N.J.R. 78(a).
Substituted "
Amended by R.2012 d.107, effective
See: 43 N.J.R. 1162(a), 44 N.J.R. 1703(a).
Rewrote (m) and ( o) through (r).
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.