N.J. Admin. Code § 17:19-2.13 - Award of contracts exceeding aggregate rating
(a) A firm
shall include with each bid a certification that the firm's bid for the subject
contract would not cause the firm to exceed its aggregate rating limits,
including consideration of its backlog of uncompleted construction work,
including public and private contracts.
(b) If at the time of a bid opening a
question arises as to whether a bid for a project is within a firm's existing
classification or aggregate rating, the bid shall be opened, and if the bid is
at variance with the firm's trade classification or aggregate rating, the bid
shall be rejected.
(c) A firm shall
not be awarded a contract which, when added to the backlog of uncompleted
construction work would exceed the firm's aggregate rating. The backlog of
uncompleted construction work shall be the total contract value of unbilled
work, as evidenced by the most recent approved invoice (or other similar
documentation) received by the bidder before or on the date of the bid. The
firm may deduct 85 percent of the total contract value of the work performed by
principal trades, as described in (e) below, on such uncompleted work. DPMC may
require the firm to provide documentary proof that its backlog of uncompleted
work plus the contract price of the contract to be awarded would not cause the
firm to exceed its aggregate rating.
(d) If a firm successfully bids for two or
more contracts which, either in combination with each other or in combination
with the backlog of uncompleted construction work on other currently held
contracts would exceed the firm's aggregate rating, the firm shall be awarded
only those contracts that in combination fall within the firm's aggregate
rating, as follows:
1. Contracts shall be
considered in the chronological order of the bid due dates.
2. Where the dollar value of a given contract
award, when combined with the dollar value of the firm's current backlog of
other uncompleted work, would cause the firm's total dollar value of
uncompleted work to exceed the firm's aggregate rating, the firm shall not be
eligible for that award.
3.
However, if a firm provides clear and convincing evidence that its total dollar
value of uncompleted work (including the bid amount for the current contract)
will be within its aggregate rating as of the award date, the Director may
determine to accept the bid if it is in the best interest of the
State.
(e) On any
project where a firm is awarded a single prime contract which encompasses work
to be performed by a subcontractor in a principal trade, as defined in
N.J.S.A.
52:32-2, including plumbing and gas fitting,
steam and hot water heating and ventilation, electrical, structural steel and
ornamental iron work, and general construction, and where the work to be
performed by the subcontractors is specifically identified in the bid, the firm
shall calculate the value of the awarded contract (for purposes of determining
how much the contract will contribute toward determining the firm's backlog) by
deducting 85 percent of the actual subcontract price of the work to be
performed by principal trades from the actual price of the contract awarded to
it. The firm will have the burden of proving that the work is encompassed by
the principal trades and the value of the amount of the work performed by those
principal trades.