N.J. Admin. Code § 2:76-24.5 - Application for the construction, installation, operation, and maintenance of a solar energy facility
(a) Any person
who owns a farm may apply for approval to construct, install, operate, and
maintain a solar energy facility by submitting an application to the Committee.
The application shall include the following information and documents:
1. A copy of the recorded deed showing the
current owner of record of the restricted premises;
2. A site plan;
3. Digital photographs showing the proposed
installation site taken from various angles and distances to show the
installation site and immediate surroundings;
4. A proposed or fully executed purchase or
lease agreement for the solar energy facilities, structures, and equipment that
clearly identifies that the owner of the qualified farm owns or will own the
facilities, structures, and equipment by the end of the term of a lease
agreement and the end date for that agreement;
5. For solar energy facilities that will
provide power, documentation from the electric distribution company that the
solar energy facilities are designed in accordance with net metering
requirements pursuant to N.J.A.C. 14:8-4; documentation showing that the solar
energy facilities will provide power directly to the farm outside of a meter;
or documentation from PJM Interconnection, LLC or the EDC showing that the
solar energy facilities will provide power directly to the electric
distribution system;
6. A copy of
the farm's electric utility bills, and/or copies of other bills, receipts, or
other documentation demonstrating the amount of electricity or fuel used to
meet the farm's energy demand for the previous calendar year; and
7. If the farm is located in the Pinelands
Area, evidence that written confirmation has been requested from the Pinelands
Commission that the solar energy facilities comply with the standards of P.L.
1979, c. 111 and the comprehensive management plan for the Pinelands Area
adopted pursuant to P.L. 1979, c. 111.
(b) Any person who owns a farm and intends to
expand a previously installed solar energy facility shall submit a new
application to the SADC.
Notes