N.J. Admin. Code § 6A:26-3.9 - Design and construction of Development Authority school facilities projects
(a) The
Development Authority shall design and construct school facilities projects in
accordance with EFCFA and the Development Authority's rules.
1. The Commissioner shall develop an
educational facilities needs assessment for each SDA district. The assessment
shall be updated periodically by the Commissioner in accordance with the
schedule the Commissioner deems appropriate for the school district; except
that each assessment shall be updated at a minimum within five years of the
development of the school district's most recent prior educational facilities
needs assessment.
2. The assessment
shall be transmitted to the Development Authority to be used to initiate the
planning activities required prior to the establishment of the educational
priority ranking of school facilities projects pursuant to this
subsection.
3. Following the
approval of an SDA district's LRFP or of an amendment to the plan, but prior to
authorization of preconstruction activities for a school facilities project
included in the plan or amendment, the Commissioner shall establish in
consultation with the SDA district an educational priority ranking of all
school facilities projects in the SDA district based upon the Commissioner's
determination of critical need in accordance with priority project categories
developed by the Commissioner. The priority project categories shall include,
but not be limited to, health and safety; overcrowding in the early childhood,
elementary, middle, and high school grade levels; spaces necessary to provide
in-district programs and services for current disabled students who are being
served in out-of-district placements or in-district programs; and services for
the projected disabled student population, rehabilitation and educational
adequacy.
4. In consultation with
the Commissioner, SDA districts, and the governing bodies of the municipalities
in which the SDA districts are situated, the Development Authority shall
establish a Statewide strategic plan pursuant to
18A:7G-5.m to be used in the
sequencing of SDA district school facilities projects based upon the projects'
educational priority rankings and issues that impact the Development
Authority's ability to complete the projects.
(b) To advance a school facilities project, a
school district that is required to use the Development Authority and has an
approved LRFP may request the initiation of preconstruction activities in
connection with a school facilities project identified as a priority project in
the Statewide strategic plan, provided that such activities are consistent with
its approved LRFP and are undertaken under the auspices of the Development
Authority.
1. School districts shall submit
to the Division a preconstruction application setting forth all preconstruction
activities - including feasibility studies, remediation, site development,
demolition, design work, acquisition of and design work for temporary
facilities, and acquisition of land - that need to be undertaken prior to
submission of a school facilities project application. The Division shall
review each application for consistency with the educational priority ranking,
the Statewide strategic plan, and the approved LRFP. If the Division authorizes
the Development Authority to undertake preconstruction activities, it shall
forward the application to the Development Authority, which shall undertake
such activities pursuant to procedures developed by the Development Authority.
Any costs incurred pursuant to this subsection shall be allocated to the
applicable school facilities project and shall be deemed eligible for a State
share.
2. For school districts in
which the State share of final eligible costs of a school facilities project is
100 percent, the Development Authority shall provide the funding for these
preconstruction costs.
(c) A school district that is required to use
the Development Authority shall seek approval from the Commissioner to acquire
land pursuant to N.J.A.C. 6A:26-7. The Commissioner may approve the land
purchase if the site is capable of supporting the applicable school facility in
the approved LRFP. If the Commissioner approves the request, he or she shall
notify the school district and the Development Authority. Any costs incurred
pursuant to this subsection shall be allocated to the applicable school
facilities project and shall be deemed eligible for a State share. For school
districts in which the State share of eligible costs for the school facilities
projects is 100 percent, the Development Authority shall provide the funding
for the cost of the land if approved by the Commissioner and the Development
Authority.
(d) The Development
Authority shall submit detailed plans and specifications to the Department for
review and approval pursuant to
6A:26-5.4. If the final plans and
specifications prepared by the Development Authority change the number, size,
location, configuration or use of educational spaces as set forth in the
detailed plans and specifications required by N.J.A.C. 6A:26-5 submitted to the
Department when a school facilities project was approved, the Development
Authority shall submit the final plans and specifications to the Department for
review and approval pursuant to N.J.A.C. 6A:26-5. For purposes of
6A:26-5.5, the detailed plans and
specifications submitted by the Development Authority shall constitute final
plans and specifications.
(e) For
all school facilities projects constructed by the Development Authority, or
which the school district is constructing under delegation of the Development
Authority pursuant to
18A:7G-13(a),
the Development Authority shall notify the Department of any change order
affecting the number, size, location, configuration or use of educational
spaces and submit the change order to the Department for review and
approval.
(f) The Development
Authority shall provide to the Division a copy of the final plans and
specifications utilized when soliciting bids for a school facilities project
and certify that no changes affecting educational adequacy were made between
the detailed plans and specifications, and the final plans and
specifications.
(g) Upon completion
of a school facilities project by the Development Authority, the school
district shall submit to the Commissioner and the Development Authority a plan
for school facility maintenance in accordance with N.J.A.C. 6A:26-20.
Notes
See: 33 N.J.R. 1809(a), 33 N.J.R. 3482(a).
Rewrote (c) through (f); in (g), inserted reference to configuration of educational spaces; and added (h) and (i).
Amended by R.2003 d.266, effective
See: 35 N.J.R. 1379(a), 35 N.J.R. 2865(b).
Deleted (b); recodified existing (c) through (i) as (b) through (h).
Amended by R.2004 d.214, effective
See: 36 N.J.R. 243(a), 36 N.J.R. 2733(b).
Rewrote the section.
Amended by R.2007 d.81, effective
See: 38 N.J.R. 4533(a), 39 N.J.R. 899(a).
Inserted "school" preceding "district" and "districts" throughout; and in (c)1, substituted "School districts" for "Districts".
Amended by R.2013 d.145, effective
See: 45 N.J.R. 1026(a), 45 N.J.R. 2557(a).
Section was "Design and construction of Authority school facilities projects". Rewrote the section.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.