N.J. Admin. Code § 7:38-11.6 - Procedures for review of an HPAA with waiver
(a) The
applicant shall demonstrate to the Department that the proposed project or
activity meets the requirements for all waivers at
7:38-6.4(e) and
complies with the special standards applicable to the waiver being sought:
7:38-6.5 (health and safety), 6.6
(brownfields redevelopment), 6.7 (70 percent impervious surface redevelopment),
6.8 (taking without just compensation) or 6.9 (construction of 100 percent
affordable housing).
(b) If the
Department determines that the project or activity satisfies the criteria for a
waiver in accordance with (a) above, the Department shall process the Water
Quality Management Plan (WQMP) amendment request that applies to the project,
if applicable, in accordance with the procedures at (c) through (i)
below.
(c) Once the Department
decides to proceed with a request to amend a WQMP, the Department shall advise
the applicant and the applicable designated planning agency, if any, in writing
of its decision. This notification shall include a public notice that shall be
given for the proposed amendment. This public notice shall announce a
non-adversarial public hearing, shall provide at least 30 days notice of the
hearing and will be published in the New Jersey Register. The public comment
period will be extended until 15 days after the hearing.
(d) At the applicant's expense, the applicant
shall:
1. Mail the public notice and request
written statements of consent under (e) below;
2. Provide a copy of the public notice to
each affected municipality;
3.
Provide for publication of the public notice in two newspapers of general
circulation in the affected area;
i. The
newspaper notices shall be published on a date to coincide with the publication
of the New Jersey Register;
ii. The
Department shall maintain a list identifying at least one of the newspapers in
general circulation that shall be used for publication of the public notice in
each Water Quality Management planning area; and
iii. The applicant shall provide proof of
publication of the notice in the newspapers to the Department. The Department
shall not act on the amendment decision until such proof of publication is
received;
4. Secure a
court stenographer; and
5. Provide
three copies of a verbatim transcript of the hearing to the Division of
Watershed Management within 30 days of the hearing.
(e) The following requirements concern
written statements of consent for plan amendments:
1. The Department shall provide a list to an
applicant identifying the governmental entities, sewerage agencies and
BPU-regulated sewer or water utilities that may be affected by, or otherwise
have a substantial interest in, approval of the proposed WQMP amendment in
accordance with (c) above. Within 15 days of receiving the list, the applicant
shall submit by certified mail (return receipt requested) a copy of the
proposed amendment to these parties, asking each entity on the list to issue
written consent to the proposed WQMP amendment within 60 days of receipt of the
request;
2. A written statement of
consent shall include a statement that the party concurs with, or does not
object to, the proposed WQMP amendment. Failure to reply or tentative,
preliminary, or conditional approval shall not be considered consent. A
statement of consent by a governmental unit shall be in the form of a
resolution by that unit's governing body. Resolutions older than one year shall
not be accepted. If the party objects to the proposed WQMP amendment, the party
shall state all reasons for objection in writing;
3. The applicant shall promptly forward to
the Division of Watershed Management a copy of all written statements of
consent and other written responses received, and a copy of all requests for
consent (with return receipts) sent to parties that did not respond at all;
and
4. Where a party denies a
request for a written statement of consent or does not reply, the reasons,
therefore, if known on the basis of reasonably reliable information, shall be
considered in making decisions under (g) below.
(f) Interested persons, including, but not
limited to, those from whom written consent is requested under (e)1 above, may
submit written comments on the proposed WQMP amendment to the Division of
Watershed Management within 15 days after the date of the public
hearing.
(g) The Department shall
prepare a written summary of public comments and responses to those comments
including the Department's decision. The Department shall either:
1. Adopt the amendment, in whole or in part,
as proposed in the New Jersey Register or with changes that do not effectively
destroy the value of the public notice; or
2. Deny the proposed amendment, in whole or
in part.
(h) The
Department shall provide written notification of the decision to the applicant
and the designated planning agency, where applicable. Notice of the final
decision shall also be published in the New Jersey Register and the DEP
Bulletin.
(i) Applicants with
projects requiring NJPDES permits will be advised at the time of public notice,
in accordance with (c) above whether or not to submit an application for a
NJPDES permit to the Division of Water Quality.
Notes
See: 37 N.J.R. 4767(a), 38 N.J.R. 5011(a).
In (a), substituted a comma for "or" preceding "6.8", and inserted "or 6.9 (construction of 100 percent affordable housing)".
Former N.J.A.C. 7:38-11.6, Final decisions, recodified to N.J.A.C. 7:38-11.7.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.