N.J. Admin. Code § 7:8-5.5 - Stormwater runoff quality standards

(a) This section contains the minimum design and performance standards to control stormwater runoff quality impacts of major development. Stormwater runoff quality standards are applicable when the major development results in an increase of one-quarter acre or more of regulated motor vehicle surface.
(b) Stormwater management measures shall be designed to reduce the post-construction load of total suspended solids (TSS) in stormwater runoff generated from the water quality design storm as follows:
1. Eighty percent TSS removal of the anticipated load, expressed as an annual average shall be achieved for the stormwater runoff from the net increase of motor vehicle surface.
2. If the surface is considered regulated motor vehicle surface because the water quality treatment for an area of motor vehicle surface that is currently receiving water quality treatment either by vegetation or soil, by an existing stormwater management measure, or by treatment at a wastewater treatment plant is to be modified or removed, the project shall maintain or increase the existing TSS removal of the anticipated load expressed as an annual average.
(c) The requirement to reduce TSS does not apply to any stormwater runoff in a discharge regulated under a numeric effluent limitation for TSS imposed under the New Jersey Pollutant Discharge Elimination System (NJPDES) rules, N.J.A.C. 7:14A, or in a discharge specifically exempt under a NJPDES permit from this requirement. Every major development, including any that discharge into a combined sewer system, shall comply with (b) above, unless the major development is itself subject to a NJPDES permit with a numeric effluent limitation for TSS or the NJPDES permit to which the major development is subject exempts the development from a numeric effluent limitation for TSS.
(d) The water quality design storm is 1.25 inches of rainfall in two hours. Water quality calculations shall take into account the distribution of rain from the water quality design storm, as reflected in Table 5-4 below. The calculation of the volume of runoff may take into account the implementation of stormwater management measures.

Table 5-4: Water Quality Design Storm Distribution
Time (Minutes) Cumulative Rainfall (Inches) Time (Minutes) Cumulative Rainfall (Inches) Time (Minutes) Cumulative Rainfall (Inches)
1 0.00166 41 0.1728 81 1.0906
2 0.00332 42 0.1796 82 1.0972
3 0.00498 43 0.1864 83 1.1038
4 0.00664 44 0.1932 84 1.1104
5 0.00830 45 0.2000 85 1.1170
6 0.00996 46 0.2117 86 1.1236
7 0.01162 47 0.2233 87 1.1302
8 0.01328 48 0.2350 88 1.1368
9 0.01494 49 0.2466 89 1.1434
10 0.01660 50 0.2583 90 1.1500
11 0.01828 51 0.2783 91 1.1550
12 0.01996 52 0.2983 92 1.1600
13 0.02164 53 0.3183 93 1.1650
14 0.02332 54 0.3383 94 1.1700
15 0.02500 55 0.3583 95 1.1750
16 0.03000 56 0.4116 96 1.1800
17 0.03500 57 0.4650 97 1.1850
18 0.04000 58 0.5183 98 1.1900
19 0.04500 59 0.5717 99 1.1950
20 0.05000 60 0.6250 100 1.2000
21 0.05500 61 0.6783 101 1.2050
22 0.06000 62 0.7317 102 1.2100
23 0.06500 63 0.7850 103 1.2150
24 0.07000 64 0.8384 104 1.2200
25 0.07500 65 0.8917 105 1.2250
26 0.08000 66 0.9117 106 1.2267
27 0.08500 67 0.9317 107 1.2284
28 0.09000 68 0.9517 108 1.2300
29 0.09500 69 0.9717 109 1.2317
30 0.10000 70 0.9917 110 1.2334
31 0.10660 71 1.0034 111 1.2351
32 0.11320 72 1.0150 112 1.2367
33 0.11980 73 1.0267 113 1.2384
34 0.12640 74 1.0383 114 1.2400
35 0.13300 75 1.0500 115 1.2417
36 0.13960 76 1.0568 116 1.2434
37 0.14620 77 1.0636 117 1.2450
38 0.15280 78 1.0704 118 1.2467
39 0.15940 79 1.0772 119 1.2483
40 0.16600 80 1.0840 120 1.2500
(e) If more than one BMP in series is necessary to achieve the required 80 percent TSS reduction for a site, the applicant shall utilize the following formula to calculate TSS reduction:

R = A + B-(AXB)/100

Where

R = total TSS percent load removal from application of both BMPs, and

A = the TSS percent removal rate applicable to the first BMP

B = the TSS percent removal rate applicable to the second BMP

(f) Stormwater management measures shall also be designed to reduce, to the maximum extent feasible, the post-construction nutrient load of the anticipated load from the developed site in stormwater runoff generated from the water quality design storm. In achieving reduction of nutrients to the maximum extent feasible, the design of the site shall include green infrastructure BMPs that optimize nutrient removal while still achieving the performance standards in N.J.A.C. 7:8-5.4 and 5.6 and this section.
(g) In accordance with the definition of FW1 at N.J.A.C. 7:9B-1.4, stormwater management measures shall be designed to prevent any increase in stormwater runoff to waters classified as FW1.
(h) The Flood Hazard Area Control Act Rules at N.J.A.C. 7:13-4.1(c)1 establish 300-foot riparian zones along Category One waters, as designated in the Surface Water Quality Standards at N.J.A.C. 7:9B, and certain upstream tributaries to Category One waters. A person shall not undertake a major development that is located within or discharges into a 300-foot riparian zone without prior authorization from the Department under N.J.A.C. 7:13.
(i) Pursuant to the Flood Hazard Area Control Act Rules at N.J.A.C. 7:13-11.2(j)4, runoff from the water quality design storm that is discharged within a 300-foot riparian zone shall be treated in accordance with this section to reduce the post-construction load of total suspended solids by 95 percent of the anticipated load from the developed site, expressed as an annual average.
(j) This section does not apply to the construction of one individual single-family dwelling, provided that is not part of a larger development or subdivision that has received preliminary or final site plan approval prior to December 3, 2018, and that the motor vehicle surfaces are made of permeable material(s) such as gravel, dirt, and/or shells.

Notes

N.J. Admin. Code § 7:8-5.5
Petition for Rulemaking.
See: 36 N.J.R. 4995(b).
Petition for Rulemaking.
See: 37 N.J.R. 141(a).
Amended by R.2016 d.055, effective 6/20/2016.
See: 47 N.J.R. 1041(a), 48 N.J.R. 1067(a).
Rewrote (h); and added (i).
Amended by R.2020 d.003, effective 3/2/2020 (operative March 2, 2021).
See: 50 N.J.R. 2375(a), 52 N.J.R. 402(a).
Rewrote the section.

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.