N.J. Admin. Code § 7:9A-3.13 - Certificate of compliance
(a)
Prior to issuance of a certificate of compliance , the administrative authority
or its authorized agent shall make sufficient inspections during the course of
construction and installation or alteration of the individual subsurface sewage
disposal system to determine that the system has been located, constructed and
installed or altered in compliance with the requirements of this chapter and
the approved engineering design . Alternatively, the administrative authority
may issue a certificate of compliance if a licensed professional engineer
submits to the administrative authority , a statement in writing, signed and
sealed by him or her that the said system has been located, constructed,
installed or altered in compliance with the requirements of these standards and
the approved engineering design .
(b) The administrative authority or
authorized agent may require additional permeability tests to be conducted, the
disposal field excavation to be deepened, fill material to be added or other
changes to be made in the installation of the system if, during the course of
excavation, soil limitations not identified previously are discovered. Such
changes shall be made as prescribed in
N.J.A.C.
7:9A-3.7.
(c) A component of an individual subsurface
sewage disposal system shall not be backfilled or otherwise concealed from view
until a final inspection has been conducted by the administrative authority or
its authorized agent , or a licensed professional engineer , and permission has
been granted by the administrative authority to backfill the system . Any
component of the system which has been covered without such permission shall be
uncovered upon the order of the administrative authority or its authorized
agent .
(d) A person shall not
commence operation or use of an individual subsurface sewage disposal system
until a certificate has been issued by the administrative authority or its
authorized agent indicating that said system has been located, constructed,
installed or altered in compliance with this chapter. The issuance of a
certificate of compliance shall constitute only certification that the
individual subsurface sewage disposal system has been constructed, located,
installed or altered in conformance with this chapter. It shall not be
construed as a guarantee that the system will function satisfactorily, nor
shall it in any way restrict the powers or responsibilities of the
administrative authority or the Department in the enforcement of any law or
ordinance relating to public health and safety or environmental
protection.
(e) The administrative
authority or its authorized agent shall give to the building inspector or
similar official of the municipality who is responsible for the issuance of
occupancy permits a copy of the certificate of compliance .