N.J. Admin. Code § 9A:18-1.5 - Grant application
(a) The Secretary
shall consider for approval grant applications that meet the funding
eligibility criteria in
N.J.A.C.
9A:18-1.4.
(b) Upon approval by its governing board at a
duly authorized meeting, an institution of higher education shall apply to the
Secretary for a project grant from the Bond Act. The institution's application
shall include the following:
1. A complete
description of the project grant to be financed with bond fund moneys,
including design information;
2. A
copy of the institutional governing board's resolution approving the
institution's application and committing the institution to support the annual
operating costs of and maintenance requirements for the proposed
project;
3. A copy of the
institution's current long-range facilities plan approved by the institution's
governing board or certification that such a plan has already been submitted to
the Secretary pursuant to
P.L.
2009 , c. 90 ;
4. A description of how the proposed project
addresses the institution's long-range facilities plan;
5. The estimated schedule for completing the
project, including cash flow requirements;
6. Cost data for the project, along with
identification of all sources of funding to be used for any costs not funded by
the grant;
7. The useful life of
any project, including equipment as determined either by reference to the
Internal Revenue Service's Class Life Asset Depreciation Range System set forth
in Revenue Procedure 87-56, as amended, supplemented, or superseded, or by
appraisal of any independent engineering or accounting firm, as
appropriate;
8. Certification by
the institution that the project will comply with all applicable laws, rules,
codes, statutes, and government guidelines, including the principles of
affirmative action and equal employment opportunity, where
applicable;
9. Certification by the
institution that it has or will have the matching funds required pursuant to
N.J.A.C.
9A:18-1.3(c);
10. Any additional information the
institution deems necessary to demonstrate how the proposed project meets the
objectives identified in
N.J.A.C.
9A:18-1.6; and
11. Other information as the Secretary may
require on a case-by-case basis and relating to a specific proposal.
(c) If the bonds issued to fund a
grant are issued on a tax-advantaged basis, including tax-exempt bonds, then in
order to receive project grant funding for expenses incurred before such bonds
are issued, such expenses must be "reimbursable" from bond proceeds under
applicable Federal tax law.
(d)
Institutions shall not use as matching funds, and grant funds may not be used
to reimburse, any expenditures made before the approval of a project grant
award, except in the discretion and upon approval by the Secretary, as
determined on a case-by-case basis, and provided that the expenditures meet the
requirements of
N.J.A.C.
9A:18-1.4.
(e) Grant applications shall be submitted in
a format provided by the Secretary.