N.M. Admin. Code § 17.7.3.8 - INTEGRATED RESOURCE PLANS FOR ELECTRIC UTILITIES
A. A public utility supplying electric
service to customers shall file with the commission every three years a
proposed integrated resource plan (IRP) to meet the service needs of its
customers over the planning period. The plan shall show the resource options
the utility intends to use to meet those needs. The plan shall also specify how
the implementation and use of those resource options would vary with changes in
supply and demand. The utility is only required to identify a resource option
type, unless a commitment to a specific resource exists at the time of the
filing. The utility shall also discuss any plans to reduce emissions from
existing resources through sales, leases, deratings, or retirements.
B. The IRP submitted to the commission by an
electric utility shall contain the utility's New Mexico jurisdictional
information as follows:
(1) description of
existing resources, see Appendix A;
(2) current load forecast, see Appendix
A;
(3) load and resources table,
see Appendix A;
(4) new load and
facilities arising from special service agreements, economic development
projects, and affiliate transactions;
(5) identification of resource options, see
Appendix A;
(6) statement of need,
see 17.7.3.10 NMAC;
(7) determination of the resource portfolio,
see Appendix A; and
(8) action
plan, see 17.7.3.11
NMAC.
C. The utilities
shall file their IRP on a staggered schedule, as follows:
(1) Public service company of New Mexico
shall file an IRP pursuant to
17.7.3.8 NMAC on or before
September 1, 2023.
(2) Southwestern
public service company shall file an IRP pursuant to
17.7.3.8 NMAC on or before
September 1, 2024.
(3) El Paso
electric company shall file an IRP pursuant to
17.7.3.8 NMAC on or before
September 1, 2025.
D. A
multi-jurisdictional utility shall include in its IRP a description of its
resource planning requirements in the other state(s) where it operates, and a
description of how it is coordinating the IRP with its out-of-state resource
planning requirements.
E. The
utility shall promptly notify the commission and participants of material
events that would have the effect of changing the statement of need or action
plan had those events been recognized when the statement of need or action plan
was accepted.
(1) The utility shall, within
two weeks of knowledge of the material event or events, submit a filing in its
most recent IRP docket detailing the material events and options being
considered as proposed modifications to the accepted action plan.
(2) This notice shall occur prior to the
development of any proposed action plan modifications to ensure that the
commission has advance notice. The utility shall serve the filing on everyone
on the service list as well as each commissioner.