To obtain prequalified status, the current version of the
prequalification packet must be obtained from the office of inspector general
through use of the department website. Each contractor and subcontractor
seeking to become prequalified shall submit its prequalification packet and any
supporting information to the department's office of inspector general as
indicated in the prequalification packet. Untimely, incomplete and
non-conforming packets will not be processed.
A. Prequalified status will be granted upon
the approval of a timely, complete and conforming prequalification packet by
the office of inspector general.
B.
An untimely, incomplete, or nonconforming
packet will result in delays
affecting prequalification status and will negatively impact the prime
contractor's ability to bid on New Mexico
department of transportation
projects.
(1) Obtaining prequalified status is
a condition to submitting a bid. Prime contractors submitting a new
prequalification packet or renewal prequalification packet must be approved no
later than seven calendar days before the opening of any bid.
(2) A prime contractor's submitting a bid
without timely obtaining prequalified status shall result in a determination
that its bid is non-responsive and the bid shall be rejected.
C. Subcontractors, at any tier,
must obtain prequalified status before performing any work on the project. Work
performed without prequalified status shall be non-compensable.
D. For prime contractors and subcontractors
who are currently prequalified by the effective date of this rule the applicant
will not need to submit a new prequalification packet until the anniversary
date of their last packet.
E.
Within five calendar days from the receipt of a
prequalification packet the
office of inspector general will provide notice of receipt of the
packet to the
contractor.
(1) If the packet submitted is
complete and conforming then the office of inspector general will provide
written notice to the applicant of approved prequalified status.
(2) If the packet submitted is incomplete or
does not conform to the requirements then the office of inspector general will
provide written notice to the applicant that the packet will not be processed
until the packet is complete and conforms to the requirements.
(3) The date of the written notice of
approved prequalified status shall establish prequalification eligibility for a
period of one year. Prequalified status shall automatically terminate if not
renewed prior to the expiration date established by the written notice of
approved prequalification status.
F. Renewal packets shall be submitted no more
than 30 calendar days before the expiration date on the document published by
the office of inspector general titled prequalified contractors and
subcontractors list. Prequalified status shall automatically terminate for the
failure to submit a timely, complete and conforming renewal packet.
Prequalified status shall be re-established upon the approval of a complete and
conforming renewal packet.
G.
Appeal of the denial of prequalification eligibility based upon the receipt of
untimely, incomplete or non-conforming packet shall be submitted in writing to
the office of inspector general with supporting documentation within seven
calendar days of the denial of prequalified status. If the appeal is untimely
the aggrieved party waives the right to appeal. The inspector general, or
designee, will issue a final written decision upholding or reversing the denial
of prequalified status within seven calendar days of the receipt of a timely
appeal. The inspector general's decision constitutes the final action taken by
the office of inspector general related to a denial of prequalified status
under this section.
H. Obtaining
prequalification status, a performance factor, or a prequalification factor
rolling average does not grant a license to do business, a right to bid or to
be awarded a contract.
I. In the
event a contractor or subcontractor is suspended or debarred, its
prequalification status shall immediately and automatically terminate without
further notice. In order to obtain renewed prequalification status after a
period of suspension or debarment a new complete and conforming
prequalification packet must be submitted and approved.