N.Y. Comp. Codes R. & Regs. Tit. 12 §§ 56-8.6 - Multiple abatement within a single regulated abatement work area
(a) Simultaneous
abatement. Simultaneous or concurrent abatement of multiple types of ACM within
a single regulated abatement work area shall not be allowed, unless the
multiple types of ACM are part of the same system (e.g., floor tile/cove base
and mastics, or ceiling/wall tile and mastic). Simultaneous removals are
allowed on a project as long as they are within different regulated abatement
work areas.
(b) Requirements for
sequential abatement. When multiple types of abatement work are done in a
common regulated abatement work area or enclosure, a sequential order of
abatement is required as shown below.
(1)
Initial plasticizing. Initial plasticizing of the containment area shall be as
required for the most stringent case of removal.
(2) Sequential removal. Sequential removal
shall allow for only one type of removal of ACM at a time in a sequential order
within the work area until that type of material is completely removed.
Thereafter, another type of ACM can be removed within the same work area.
Relief from plasticizing is for the surfaces to be abated only at the time of
that specific material abatement. Other surfaces shall be plasticized as the
material being abated dictate, except as noted below.
(i) Order of sequential abatement. The
following sequence of abatement within a work area shall begin at the ceiling
or upper level and progress one material at a time down to the floor and from
most friable material to least friable material.
(ii) Example:
(a) First. All ceiling fireproofing, ceiling
plaster or similar ceiling OSHA Class I friable material shall be completely
abated so that no visible exposed ACM, PACM or asbestos material remains. Then
the friable mechanical/tank insulation, isolation/ vibration damper material
and thermal pipe, ducts, pipe fitting insulation, mudded firebrick, or similar
OSHA Class I or Class II friable material shall be completely abated so that no
visible exposed material remnants remain. Glovebags may be used. After all
friable ACM has been abated, the area shall be cleaned of all debris/residue
using HEPA vacuuming and wet wiping.
(b) Second. OSHA Class II non-friable
materials shall be abated. If other areas/surfaces were abated, no new
plasticization shall be required. Ceiling and wall tiles, transite, interior
window glazing, expansion joint, millboard and other NESHAP Category I and II
non-friable ACM shall be abated so that no visible exposed material remnants
remain and the area shall be cleaned of all debris/residue using HEPA vacuuming
and wet wiping.
(c) Last. OSHA
Class II non-friable flooring abatement shall be last. Non-friable ACM flooring
materials and ACM mastic shall be abated so that no visible exposed material
remnants remain and the area shall be cleaned of all debris/residue using HEPA
vacuuming and wet wiping. If beadblaster or a similar abrasive type of
abatement method is used, full work area preparation, including establishment
of negative pressure filtration systems, shall be required and this abatement
may be done as one of the first types of abatement and then the flooring area
abated shall be re-plasticized with a double-layer of six-mil fire-retardant
plastic sheeting, to be utilized as a dropcloth during the remaining
abatement.
(iii)
Temporary walls. New temporary hardwalls used to separate an enclosed regulated
abatement work area into smaller regulated abatement work area enclosures shall
be constructed as per section
56-7.11(b) of
this Part. Existing columns, I beams and interior walls may be used to support
or to act as part of the new containment walls provided that the existing
walls, columns, and I beams to which these temporary walls are to be attached
or used shall be completely abated prior to the erection of these new
containment walls to allow this attachment. Caulk, fire-retardant expandable
foam or duct tape shall be used to form an airtight seal for these partitions.
(a) Airlock. Each newly enclosed regulated
abatement work area shall have an attached airlock as defined in section
56-2.1 of this Part, and the
airlock shall be constructed at the enclosure entrance, as per section
56-7.5(b)(11) of
this Part. Each enclosure and airlock shall be cordoned off 25 feet from its
perimeter. Critical openings within the cordoned off area shall be covered with
two layers of six mil fire-retardant polyethylene in conformance to section 56-
7.11(a) of this Part.
(iv) Intermediate completions. On completion
of each type of asbestos abatement within these work area enclosures, a
complete single clean of all surfaces in the entire area - ceiling, walls and
floors - shall be performed by HEPA vacuuming and wet wiping. No final
clearance air samples shall be required for each individual type of material
abatement, until the last type of ACM, PACM or asbestos material is abated.
Each intermediate completion shall include a visual inspection for completeness
by the supervisor. Results of the visual inspection and time of intermediate
completion shall be documented by the supervisor in the daily project
log.
(v) Final required cleaning. A
complete single clean of all surfaces in the entire area -- ceiling, walls and
floors, followed by a visual inspection as described in Subpart 56-9 of this
Part shall be performed by HEPA vacuuming and wet wiping, after all abatement
is complete.
(vi) Final clearance
air samples. After the final cleaning and visual inspection requirements are
completed and the final settling/drying period is observed, prior to
dismantling the regulated abatement work area, Phase IIC final clearance air
samples shall be collected and satisfactory clearance air results obtained as
per section
56-9.2 of this Part.