N.Y. Comp. Codes R. & Regs. Tit. 12 §§ 56-9.1 - Final cleaning procedures
The following cleanup procedures shall be required after completion of Phase II B activities:
(a) Continuous negative pressure ventilation.
If required during Phase II B, the negative pressure ventilation units shall
remain in continuous operation during implementation of Phase II C, including
observance of settling/waiting periods and drying times.
(b) First cleaning, lockdown encapsulation
and top layer removal. All surfaces of the regulated abatement work area shall
be first wet-cleaned using rags, mops and sponges. For collecting excess liquid
and wet debris, a wet purpose HEPA filtered shop vacuum may be used and shall
be emptied prior to removal from the regulated abatement work area. When the
first cleaning has been completed, a thin coat of a lockdown encapsulant agent
shall be applied to all surfaces within the regulated abatement work area which
were not the subject of removal or abatement. In no event shall lockdown
encapsulant be applied to any surface which was the subject of removal or other
abatement response activity, prior to obtaining satisfactory clearance air
results for the regulated abatement work area. Once the lockdown encapsulant
has been applied, and the appropriate waiting/settling or drying time
requirements of this Subpart have been met, the cleaned, exposed top barrier
layer of plastic sheeting shall then be removed from walls, ceilings and
floors. Windows, doors, HVAC system vents and other openings shall remain
sealed. Decontamination system enclosures shall remain in place and shall
continue to be utilized.
(c) Second
cleaning and bottom layer removal. After the top layer of plastic sheeting has
been removed, all objects and surfaces in the regulated abatement work area
shall be HEPA-vacuumed and then wet-cleaned. After the second cleaning and
waiting/settling or drying time requirements of this Subpart, then the
remaining bottom layer of plastic sheeting on walls, ceilings and floors shall
be removed. All windows, doors, HVAC system vents and all other openings shall
remain sealed.
(d) Third or final
cleaning and visual inspection. After the bottom layer of plastic sheeting has
been removed, all objects and surfaces in the regulated abatement work area
shall be HEPA-vacuumed and then wet-cleaned. After the final cleaning is
complete, clearance air sampling shall not commence until the appropriate
waiting/settling or drying time requirements of this Subpart have elapsed and a
visual inspection has been completed by the project monitor to confirm that the
scope of abatement work for the asbestos project is complete, and no visible
asbestos debris/residue, pools of liquid, or condensation remain. The asbestos
abatement contractor supervisor must complete a satisfactory visual inspection
for completeness of abatement and cleaning, prior to commencement of the
project monitor visual inspection.
(1)
Project monitor visual inspection. An appropriately trained and certified
project monitor, contracted by the building/structure owner, independent of the
asbestos abatement contractor, shall complete the visual inspection. The
project monitor visual inspection for completeness of abatement and
completeness of cleanup shall be performed as per the provisions of the current
ASTM standard E1368 "Standard Practice for Visual Inspection of Asbestos
Abatement Projects". If the property owner is the asbestos abatement contractor
for the asbestos project, the owner shall contract with an independent project
monitoring firm asbestos contractor for the necessary visual inspection on the
asbestos project. The asbestos abatement contractor and property owner, prior
to the scheduling of the required visual inspection, shall provide a complete
abatement scope of work for the asbestos project to the project monitor. An
entry shall be made into the asbestos abatement contractor supervisor's daily
log by both the supervisor and the individual performing the inspection,
detailing the findings of the visual inspection. The full name and NYSDOL
asbestos handling certificate number of the certified individual performing the
inspection shall also be documented in the supervisor's daily log.
(e) Exemption from multiple
cleaning and sheeting removal. When the regulated abatement work area is not
required to be plasticized, or when a tent enclosure unit is used, one thorough
final cleaning followed by the observance of the appropriate waiting/settling
or drying time requirement of this Subpart shall be required. For regulated
abatement work areas where one layer of plastic sheeting is allowed, such as
the use of spray plastic or pre-demolition asbestos projects, two cleanings
(first and final), each followed by observance of the appropriate
waiting/settling or drying time requirements of this Subpart is required.
Cleanings shall consist of all surfaces in the regulated abatement work area
being HEPA vacuumed first and then wet-cleaned.
(f) Waiting/settling and drying times
requirements. For sequential removals as per section
56-8.6(b) of this
Part, the most stringent waiting/settling/drying time shall be observed.
(1) The following waiting and drying times
per material abated shall be observed for each stage of cleaning as per this
Subpart:
(i) fireproofing, plaster, TSI and
other friable materials -12 hours
(ii) abrasive removals of floor tile/mastic
with machinery -12 hours (such as a bead blaster, grit blaster, etc.)
(iii) manual removal of floor
tiles/mastic - 4 hours
(iv) manual
abatement of interior non-friable materials - 4 hours
(v) incidental disturbance asbestos project -
4 hours
(vi) tent with glovebag
abatement of TSI - 2 hours
(vii)
intact transite panel removals indoors - 2 hours
(viii) Exterior non-friable ACM abatement
without negative pressure enclosure - None
(h) Decontamination of tools and equipment.
All equipment (except negative air ventilation system) and tools shall be
removed from the regulated abatement work area and properly decontaminated as
per this Part, prior to commencement of clearance air sampling.