N.Y. Comp. Codes R. & Regs. Tit. 12 §§ 56-9.3 - Dismantling of regulated abatement work area
(a) Collapsing and containerizing of tent
enclosures. Each tent enclosure and airlock shall not be dismantled until
clearance air sampling has been performed and satisfactory results obtained.
The plastic sheeting which formed the tent, airlock, and the contents thereof,
shall be fully collapsed, starting from the top and working downward. The tent
and contents shall be placed in at least a six mil plastic bag or hardwall
container, sealed airtight with duct tape and removed for disposal. The plastic
sheeting shall be treated as contaminated material and properly disposed of as
asbestos waste.
(b) Removal of
tools and equipment. All remaining tools and equipment shall be removed from
the regulated abatement work area after proper decontamination as per this
Part.
(c) Removal of remaining
barriers. Once the asbestos abatement contractor receives satisfactory
clearance air sample results, or an acceptable visual inspection for an exempt
regulated abatement work area, and all tools and equipment are removed, all
remaining polyethylene, duct tape, expandable foam and other barrier materials
shall be bagged, wrapped or containerized and labeled as asbestos waste.
Temporary hardwall barriers must be dismantled and removed from the site. If
any debris/residue is observed behind barriers, it shall be removed and
bagged/containerized followed by HEPA-vacuuming and wet-cleaning of the
surfaces that were hidden behind the barrier. All waste generated shall be
removed to the holding area, lockable trailer or lockable hardtop dumpster as
per section
56-8.9 of this Part. The asbestos
abatement contractor's supervisor shall then conduct a final inspection of the
regulated abatement work area to certify that the abatement work is complete
and no debris/residue remains. The results of the final inspection for each
regulated abatement work area shall be noted in the asbestos abatement
contractor supervisor's daily project log.
(d) Removal of decontamination enclosure.
After all other remaining isolation barriers, tools and equipment have been
removed from the regulated abatement work area, the remaining decontamination
enclosure for the regulated abatement work area must be dismantled and removed
from the work site. All plastic sheeting shall be removed and disposed of as
asbestos waste.