N.D. Admin Code 89-04-05-01 - General
Overland flow from undisturbed areas may, if required or approved by the state engineer, be diverted away from disturbed areas by means of temporary or permanent diversion structures. The following requirements shall be met:
1. Temporary diversion
structures are those used during mining and reclamation. When no longer needed,
these structures shall be removed and the area reclaimed. Temporary diversion
structures shall be constructed to safely pass the peak runoff from a
precipitation event with a ten-year recurrence interval, or a larger event as
specified by the state engineer.
2. Permanent diversion structures are those
remaining after mining and reclamation and approved for retention by the state
engineer and other appropriate state and federal agencies. To protect fills and
property and to avoid danger to public health and safety, permanent diversion
structures shall be constructed to safely pass the peak runoff from a
precipitation event with a hundred-year recurrence interval, or a larger event
as specified by the commission. Permanent diversion structures shall be
constructed with gently sloping banks that are stabilized by vegetation.
Asphalt, concrete, or other similar linings shall not be used unless
specifically required to prevent seepage or to provide stability and are
approved by the state engineer.
General Authority: NDCC 28-32-02, 61-02-11, 61-03-13
Law Implemented: NDCC 61-02-14